Night closures mean rough ride continues for downtown Port Angeles

PORT ANGELES — An unplanned delay in asphalt paving means motorists will continue having a rough ride on busy Front Street between Oak Street and Marine Drive this week.

And nightly, blocklong downtown road closures will begin Wednesday.

Paving slated to begin last week on the churned-up road surface is now expected to be completed between July 5 and July 31, City Engineer Mike Puntenney said Friday.

“Lakeside [Industries] has too many other commitments in the queue,” he said.

The road surface had been broken up during the city’s $15.2 million phase two installment of the combined sewer overflow (CSO) project.

It will remain gravelly and rough for the time being.

“It’s not pleasant,” Puntenney acknowledged.

The project includes laying a new sewer main east from Marine Drive to Lincoln Street that will then turn south to Second Street.

Its installation will prompt the nighttime road closures for about three weeks beginning Wednesday and lasting four to five weekday nights a week.

TEK Construction of Bellingham, the contractor for the sewer-main portion of the project, will close one lane from 7 p.m. to 10 p.m. to accommodate ferry traffic and both lanes — the entire block — from 10 p.m. to 6 a.m.

The First Street closures will occur between intersecting streets: from Oak to Laurel, Laurel to Lincoln, Lincoln to First Street and First to Second.

Intersecting streets will remain open, as will all sidewalks, providing access to local businesses.

“There will be noise during that time frame, there’s no doubt about that,” Puntenney said earlier last week.

He said it won’t be as disruptive as the citywide din caused by pile-driving for the ongoing pump-station portion of the CSO project.

“There may be some noise they can hear along the bluff,” he said.

“We’re hoping that in front of any one particular building that it is a day or two of inconvenience.”

The Fourth of July parade will not be affected by the project.

Once the sewer line is installed — by July 31 — construction on phase two will be confined to the pump station where Marine Drive blends into First.

Construction is expected to begin on the two-story pump station by mid-July.

It will replace the pump station across the street, which will be demolished, allowing complete access to Valley Creek Estuary Park.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 5060, or at pgottlieb@peninsuladailynews.com.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

The aurora borealis shines over Port Townsend late Monday night. Ideal conditions to view the event are from about 9 p.m. to 3 a.m. with clear skies and away from city lights or higher locations with northern views. (Steve Mullensky/for Peninsula Daily News)
Northern lights

The aurora borealis shines over Port Townsend late Monday night. Ideal conditions… Continue reading

Jefferson County board sets annual goals

Discussions include housing, pool, artificial intelligence

Clallam commissioners to continue policy discussions on RVs, ADUs

Board decides to hold future workshop before finalizing ordinance

Port Angeles School District community conversation set Thursday

Individuals who want to talk to Port Angeles School… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading