New kitchen in sight for Sequim school district

SEQUIM — Sequim School District has a clearer vision of what its new central kitchen will look like now that an option has been approved for the district’s capital projects.

The Sequim School Board on Monday unanimously approved option three that renovates the west wing of the Sequim Community School into a new central kitchen and deconstructs the remaining portions of the building.

This plan will cost $5.36 million, funded by the district’s $5.75 million budget generated from a capital projects levy voters approved in February of 2017.

It also allows the district to apply for $4.1 million in state matching funds plus an additional $1 million because it allows more square footage to be counted toward matching dollars.

Board President Heather Short said Monday that from what she gathered from the 12 public forums held during the past several weeks that option three was the most accepted plan among those who attended.

This option creates a new kitchen that allows for an efficient layout of kitchen equipment for kitchen staff operations and for the possibility of a new school in the future.

The location of the kitchen on site can be optimized for new school construction. It will be 100 percent code-compliant and include all new systems for the lowest long-term maintenance impacts.

It also will shift the loading and unloading operations of trucks that deliver food to other schools in the district to be separated from school operations to optimize student safety.

OPA concerns

While this plan is in the district’s budget and allows for more state matching funds, it will require that Olympic Peninsula Academy (OPA) relocate.

The central kitchen will not need to relocate during deconstruction but will remain in its current location until the new kitchen is constructed.

OPA is an alternative learning experience program that consists of 100 students and nine classrooms. One classroom has already been relocated from the community school to a new site in the district over the winter break because of water saturation levels from a leaky inverted roof in the community school that forced the classroom to move.

A few OPA parents spoke up during public comments at the meeting Monday.

“We would like to be more than just a program,” OPA parent Kaylene Byrne said. “Given all the options impact OPA, our concerns are high regarding displacement and a temporary solution.”

She suggested an OPA advisory group be put together to include staff and parents as the Board and the district move forward with its capital project plans.

“We would really like to request some sort of OPA advisory group be put together,” Byrne said.

Jeanette Gish, who has been an OPA parent for one year with a son at the high school level, asked what the long-term plans are for OPA as well as what a permanent solution looks like.

“I would really like to see it continue and I’m concerned it’s on the back burner,” she said.

She asked why the district is choosing to build a new kitchen first instead of a new school.

“I would think rebuild the school first and then accommodate a fancy kitchen,” she said. “And I think OPA should be considered on that level.”

Neal said he spoke with OPA parents Monday afternoon and confirmed the district is trying to find a temporary and a permanent solution for OPA.

Board member Brandino Gibson said the board and the district want to keep all nine OPA classes together by relocating them all to one location in the future.

Neal said the intention was that OPA was going to stay for the remainder of the year so those services would not be interrupted, but with the water saturation levels accruing in the community school the district would most likely have to move OPA despite the options presented with capital projects.

“With [the community school and commons area] falling apart and the saturation taking place, we would have to come up with a plan for OPA,” he said. “Regardless this is going to be an issue.”

Short said to her knowledge OPA could tentatively move to a new location by the start of the next school year but classes could move sooner if more water saturation occurs in the building.

She said Neal has been in contact with community leaders such as the Jamestown S’Klallam Tribe, the city of Sequim and realtors to find a viable option for OPA at this point. Option three does provide funding to relocate OPA but as to where has not been decided yet.

Short said the board and the district plan to be in communication with OPA parents and staff and believes the idea of an OPA parent advisory group is a good one.

“None of us [the board] felt comfortable making a decision of this magnitude that affects so many students and taxpayer dollars without community input,” she said.

________

Erin Hawkins is a reporter with the Olympic Peninsula News Group, which is composed of Sound Publishing newspapers Peninsula Daily News, Sequim Gazette and Forks Forum. Reach her at ehawkins@sequimgazette.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading