The biomass burner unit at the Nippon Paper Industries USA cogeneration facility has a distinctive conical shape reminiscent of the Northwest's “teepee burners” of generations ago. — Photo by Keith Thorpe/Peninsula Daily News ()

The biomass burner unit at the Nippon Paper Industries USA cogeneration facility has a distinctive conical shape reminiscent of the Northwest's “teepee burners” of generations ago. — Photo by Keith Thorpe/Peninsula Daily News ()

Multimillion dollar lawsuits filed over Nippon Paper’s Port Angeles biomass plant

PORT ANGELES — Nippon Paper Industries USA and a Louisiana company have filed competing, multimillion-dollar lawsuits over Nippon’s stalled biomass cogeneration plant.

Factory Sales & Engineering Inc., now doing business as FSE Energy, filed its $6.2 million breach-of-contract lawsuit against Nippon Nov. 10 in U.S. District Court.

Nippon’s Dec. 8 answer was a three-pronged, $10.85 million claim against FSE alleging breach of contract, negligence and negligent misrepresentation.

Since both companies are also seeking attorney fees, a final award could exceed the stated amount each is seeking.

The issue: Who is responsible for a leaky, cracked boiler at Nippon’s upgraded, costlier-than-expected, $85 million biomass cogeneration plant?

The plant burns biomass — or wood waste — to create steam that generates electricity that the company can sell to others.

The companies have until Jan. 28 to hold a telephone conference with Western U.S. District Court Judge Robert J. Bryan of Tacoma to discuss the basis of their claims and a possible settlement, according to court documents.

A case schedule will be set at a Feb. 11 status conference.

Most civil cases are ready for trial within a year of the status conference, according to a Nov. 13 court order that scheduled dates in the case.

“I don’t believe there’s any discussion on settling,” Nippon mill Manager Steve Johnson said Thursday.

“At this point, there’s no reason to believe otherwise.”

An FSE company official who identified himself as the chief operating officer but would not give his full name would not comment on the case Thursday.

“You don’t even need to do a story on this,” he said.

FSE’s website at www.fseenergy.com identifies Chris Pulver as the company COO.

Seattle lawyer Miles Stanislaw, representing FSE, did not return calls for comment Wednesday and Thursday.

Seattle lawyer Blake Marks Diaz, representing Nippon, would not comment on the case Thursday.

The plant was dedicated in November 2013 but has been plagued by delays in operating at full capacity.

A mud-drum — a key component of the boiler that was built by Covington, La.-based FSE Energy — has since been replaced and is now creating steam for the factory and electricity for sale, Johnson said Thursday.

The 30-foot, 25 ton pressurized mud drum holds water and traps mud and sediment to prevent it from circulating.

The dispute about who should pay for what to remedy the situation entered the legal arena a year after the cogeneration plant was dedicated by officials from Nippon’s Tokyo-based parent company, Nippon Paper Industries Co. Ltd.

According to the FSE’s lawsuit, the company had sent Nippon an invoice for $43.7 million for the cogeneration project under an original contract estimated at $38.9 million.

FSE is seeking a jury trial to address its allegation that Nippon breached its contract by still owing the company $3.7 million of invoiced charges and retention fees, $1.6 million for change orders and for extra work performed by FSE, more than $900,000 in 18-percent-interest charges for overdue payments by Nippon and an unspecified amount in delay damages.

FSE blamed Nippon for incorrectly operating the boiler under a contract the companies signed Nov. 3, 2010.

For example, FES said that Nippon repeatedly hosed down the empty, hot mud drum — the one that was eventually replaced — with cold water, “causing stress fractures in it due to thermal shock,” according to the lawsuit.

FSE also alleges Nippon repeatedly burned fuel that was not in compliance with contract specifications and that the factory experienced outages “which tripped the boiler system constructed by FSE,” according to the lawsuit.

“Similar problems were continuously cause by [Nippon Paper Industries] throughout FSE’s efforts to commission the boiler,” the lawsuit said.

“NPI’s wrongful actions and inactions prevented the necessary flow of heat and water for the boiler to operate properly.

“Any damage to the boiler or damage to its component parts and pieces was proximately caused by NPI or third parties, who NPI had control over and responsibility for.”

In its countersuit, Nippon denied responsibility for the boiler problems and said FSE was at fault.

FSE began construction of the boiler in June 2012 and was to complete construction by July 28, 2013, or four months before the cogeneration plant’s dedication, according to the lawsuit.

Holes and cracks in the mud drum tube joints that were leaking and weeping water were discovered from January 2014 through at least March 2014, Nippon said.

“FSE procured and supplied the mud drum for the boiler,” the suit said.

“The mud drum installed in the boiler was defective.

“Because the tubes were not properly rolled into the mud drum, the entire mud drum had to be replaced.

In addition, a mud drum and adjacent steam drum “were installed out of alignment by more than an inch,” the suit said.

“The undersized steam drum adversely affected the steam quality and caused carryover of water droplets and contaminants that damaged the turbine blades.”

FSE’s breaches-of-contract include failing to ensure equipment was new and of good quality, failing to complete its work on time, providing defective work, and “failing to provide a new, working boiler as promised,” according to Nippon’s lawsuit.

Nippon is seeking damages that include more than $6 million for replacing the mud drum and generating tube bank, $2 million to complete unfinished work and correct other defective work, more than $1 million to correct steam-drum level-control issues and at least $300,000 for delay in delivery.

The old boiler, which created steam but not electricity, is now fully off-line, Johnson said.

The new boiler has been creating steam for the plant and producing “for the most part” about 14-15 megawatts for sale since mid-December but not the full 20 megawatts it was intended to generate, Johnson said.

“The reliability has been good. It’s been up,”he said.

“Before you know it, we’ll be there.”

Johnson said air-quality testing on the new plant will begin later this winter and predicted the new boiler will be fully operational by mid-March.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 5060, or at pgottlieb@peninsuladailynews.com.

More in News

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas and Sue Authur, and Main Street employees, Sasha Landes, on the ladder, and marketing director Eryn Smith, spend a rainy morning decorating the community Christmas tree at the Haller Fountain on Wednesday. The tree will be lit at 4 p.m. Saturday following Santa’s arrival by the Kiwanis choo choo train. (Steve Mullensky/for Peninsula Daily News)
Decoration preparation

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas… Continue reading

Port Angeles approves balanced $200M budget

City investing in savings for capital projects

Olympic Medical Center Board President Ann Henninger, left, recognizes commissioner Jean Hordyk on Wednesday as she steps down after 30 years on the board. Hordyk, who was first elected in 1995, was honored during the meeting. (Paula Hunt/Peninsula Daily News)
OMC Commissioners to start recording meetings

Video, audio to be available online

Jefferson PUD plans to keep Sims Way project overhead

Cost significantly reduced in joint effort with port, city

Committee members sought for ‘For’ and ‘Against’ statements

The Clallam County commissioners are seeking county residents to… Continue reading

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on Saturday at the Airport Garden Center in Port Angeles. All proceeds from the event were donated to the Peninsula Friends of Animals. (Dave Logan/for Peninsula Daily News)
Santa Paws

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on… Continue reading

Peninsula lawmakers await budget

Gov. Ferguson to release supplemental plan this month

Clallam County looks to pass deficit budget

Agency sees about 7 percent rise over 2025 in expenditures

Officer testifies bullet lodged in car’s pillar

Witness says she heard gunfire at Port Angeles park

A copper rockfish caught as part of a state Department of Fish and Wildlife study in 2017. The distended eyes resulted from a pressure change as the fish was pulled up from a depth of 250 feet. (David B. Williams)
Author to highlight history of Puget Sound

Talk at PT Library to cover naming, battles, tribes

Vern Frykholm, who has made more than 500 appearances as George Washington since 2012, visits with Dave Spencer. Frykholm and 10 members of the New Dungeness Chapter, NSDAR, visited with about 30 veterans on Nov. 8, just ahead of Veterans Day. (New Dungeness Chapter DAR)
New Dungeness DAR visits veterans at senior facilities

Members of the New Dungeness Chapter, National Society Daughters of… Continue reading

Festival of Trees contest.
Contest: Vote for your favorite tree online

Olympic Medical Center Foundation’s Festival of Trees event goes through Dec. 25