Morse Creek fish crib nears completion as preparations continue for removal of Elwha, Glines Canyon dams

PORT ANGELES — The state Department of Fish and Wildlife is gearing up to open a $2.1 million fish-rearing structure at Morse Creek near the U.S. Highway 101 S-curve east of Port Angeles to preserve the endangered Elwha River chinook salmon.

Pete Fisher, on-site foreman for the state Department of Fish and Wildlife, said the project is expected to be completed by the middle of this month.

“It’s getting close,” Fisher said.

The state has a 10- to 12-person crew working overtime to get fish in the ponds sometime between Feb. 15 and 22.

“It’s shaping up,” said Ray Berg, Fish and Wildlife Engineer and Project Manager.

No public ceremony is planned for the opening.

The fish crib is part of a $308 million project to remove the two Elwha River dams and restore the stream back to its natural state. It is being funded by the National Park Service.

The facility is being built on Morse Creek rather than the Elwha River to get 200,000 juvenile hatchery-born Elwha River salmon acclimated to Morse Creek.

Removal of the Elwha and Glines Canyon dams — slated to begin in 2011 — carries a risk that the Elwha River salmon population could be wiped out by the large amount of sediment that will be released.

Conditions in the lower Elwha River may become temporarily unsuitable for salmon.

By raising some salmon in Morse Creek, the facility will preserve their genetic makeup if such an extinction occurs.

The same salmon, which will be marked, could then be used to replenish the Elwha River stock if needed, Berg said.

Construction of the facility began in early September. It was originally scheduled to open in December.

“It keeps getting pushed back,” Fisher said.

Berg said the delays were construction-related and routine. The delays did not change the cost estimate.

“There hasn’t been any substantive hang ups,” he said.

Four 100-feet-long, 10-feet wide and 5-feet-deep rearing ponds will hold the juvenile salmon, and a 1,350-square foot fiberglass pond will control pollution.

The rearing ponds will siphon from 1,600 to 2,400 gallons of water from Morse Creek per minute. The water will be returned to the stream at the same rate.

The Clallam County Public Utility District is providing electricity to the site. PUD crews erected a power pole north of U.S. Highway 101 near the facility on Thursday.

“We are essentially extending service to that site,” said Jeff Beaman, PUD spokesman.

Crews planned to temporarily close both lanes of the highway in the early morning hours today — sometime between 11 p.m. and 5 a.m. — so the PUD could span a line from the south side of the highway to the north side.”

Beaman said there is nothing unusual about the medium service capacity power line.

The state will install an electrical panel and have the connection certified and inspected.

“Then we’ll install the meter,” Beaman said.

The facility will raise juvenile Elwha River chinook salmon for 12 years before it is demolished.

Meanwhile, groundbreaking for a new Elwha River salmon hatchery is scheduled for Friday.

The dam removal project will be the largest National Park Service restoration project except for the revival of the Florida Everglades.

________

Reporter Rob Ollikainen can be reached at 360-417-3537 or at rob.ollikainen@peninsuladailynews.com.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

The aurora borealis shines over Port Townsend late Monday night. Ideal conditions to view the event are from about 9 p.m. to 3 a.m. with clear skies and away from city lights or higher locations with northern views. (Steve Mullensky/for Peninsula Daily News)
Northern lights

The aurora borealis shines over Port Townsend late Monday night. Ideal conditions… Continue reading

Jefferson County board sets annual goals

Discussions include housing, pool, artificial intelligence

Clallam commissioners to continue policy discussions on RVs, ADUs

Board decides to hold future workshop before finalizing ordinance

Port Angeles School District community conversation set Thursday

Individuals who want to talk to Port Angeles School… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading