More asbestos than expected raises cost of Port Angeles landfill stabilization by $1 million

PORT ANGELES — The city of Port Angeles will ante up an additional $1 million to dispose of asbestos it didn’t expect to find as it stabilized its closed landfill.

The change order in the amount of $1,034,524 will bring the project’s cost to at least $14.4 million.

The asbestos was part of the 400,000 cubic yards of trash the city is moving away from a bluff above the Strait of Juan de Fuca in the wake of the discovery that the material was threatening to tumble into the Strait.

The landfill at the end of West 18th Street was closed in 2007, and the area became the city’s transfer station.

Four years later, it was found that the erosion in the bluff above the Strait had exposed garbage that could eventually fall into the water.

Work began last summer to move the refuse about a quarter-mile south. The whole project is expected to be finished next fall.

Most of the asbestos work already has been performed by contractor Magnus Pacific Corp. of Everett, which trucked away more than three times the asbestos it anticipated — some 49 tons — under a contract that called for it to dispose of about 15 tons.

Asbestos that engineers thought could be dug up with hand tools and put into bags wound up being handled with excavators that filled dump trucks, according to Craig Fulton, city public works and utilities director.

“The contractor has completed the work, so they have expended a considerable amount of money to remove the asbestos,” Fulton said.

The work, performed with the help of the state Department of Labor and Industries, required workers to wear protective clothing and hose down vehicles with water cannons.

“There was a clear impact to their productivity when they uncovered the asbestos,” Fulton told City Council members at their meeting Tuesday night.

The contractor and the city remain “very far apart” — to the tune of $2,075,508 — he added, over the added cost of the asbestos removal. Magnus Pacific wants an adjustment of $3,110,032.

“The negotiations are still ongoing. We may have to go into mediation,” Fulton said.

The $1 million-plus the council approved Tuesday, however, will allow Magnus Pacific to pay its workers. Meanwhile, the city may bill the state for the work, he said.

The initial payment, at least, will come from $1.7 million that remains in contingency funds for the project, Fulton said, and the city may be able to get more money from a state trust fund.

“It’s ironic that we can’t see what’s underground,” said Councilman Lee Whetham.

“But that’s part of construction, and that has to be anticipated. We haven’t even hit bottom yet.”

Councilman Dan Gase asked if all the asbestos had been removed from the landfill site.

Fulton said a 3-D image of the area shows only about 2,000 cubic yards remain, compared with the 7,283 cubic yards Magnus Pacific already has removed.

The remainder should be removed in May.

“It’s in a smaller area,” Fulton said. “We can isolate that and continue with the waste removal in the rest of the area.”

The entire landfill stabilization will relocate approximately 400,000 cubic yards of garbage.

The Labor and Industries Department, Fulton said, was innovative in its bulk-handling approach to the asbestos problem.

“That saved millions of dollars,” he said.

Still, he added, the total bill for moving the refuse and stabilizing the area could top $21 million.

________

Reporter James Casey can be reached at 360-452-2345, ext. 5074, or at jcasey@peninsuladailynews.com

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading