Major work at The Gateway still on hold

PORT ANGELES — After months of little or no activity, jack hammering could be heard echoing from the east side of The Gateway in downtown Port Angeles on Tuesday.

But the sound of metal chiseling away concrete does not mean the completion of the project that has been delayed since cracks underneath a concrete beam were discovered in September in the parking garage beneath the project’s pavilion.

The work done Tuesday was cosmetic.

No decision has been made about the structural integrity of the building after the cracks under the concrete beam were discovered.

“We’re just doing punch-list items,” said Roland Ordona, Primo Construction site superintendant, on Tuesday.

“We’re fixing slabs down below that had cracks in them.”

These cracks, located in a floor-slab of concrete just north of the pavilion, weren’t a safety concern, but were “visually unacceptable.”

A Primo employee chiseled away at the top layer of the slab Tuesday to allow a new layer to be poured.

The joint city of Port Angeles and Clallam Transit project — located at Front and Lincoln streets and Railroad Avenue — is budgeted at $14.7 million by the city.

It includes a transit center, parking garage, pavilion and police substation.

The city and Clallam Transit received $8.1 million in state and federal grant funding for The Gateway.

Ordona said Primo has had a skeleton crew of one or two people at the site when there is work that can be done, since at least early November.

Major work has been hold there while the city resolves safety concerns with the structural integrity of the pavilion.

Until that is done, Primo cannot pour a second slab of concrete on the plaza floor in the pavilion because, after the cracks appeared, the city wants to ensure that the structure can support the additional weight.

That work item is the last non-aesthetic job to be done on The Gateway.

Glenn Cutler, city public works director, said last week that the city is still waiting for questions to be answered about the design of The Gateway by Krei Architecture and Bright Engineering, Inc, both of Seattle.

“We’re looking at structural issues,” he said, adding that the cause of the cracking has yet to be determined.

“I can’t say if it’s the concrete mix, steel design, steel tension.

“I don’t know that specific.”

A probable cause identified by Cutler in November is the “post-tensioning process” used in the horizontal concrete beams that support the pavilion. With this method, intended to add strength, steel wires within the concrete are pulled taut.

Completing The Gateway will require an extension of Primo’s $8 million contract with the city.

Ordona said that still needs to be negotiated, and he didn’t know how many work days were left in the original contract.

Ordona said that the cold, wet weather last month has not affected the structural integrity of The Gateway’s buildings.

During that time water pipe froze and burst, but was fixed, he said.

The second slab of concrete will allow for better water drainage on the pavilion floor, where puddles of water remain for days after rainfall and snow melt.

According to city Finance Director Yvone Ziomkowski, major costs for The Gateway include:

• About $8 million to Primo.

• About $3 million for property acquisition, done by Clallam Transit.

• $616,000 to Exceltech, which is managing the project.

• $412,728 Krei contract, which includes design review during construction.

• About $200,000 for signs for The Gateway.

Clallam Transit has provided $500,000 toward the project, in addition to the money for acquiring property.

________

Reporter Tom Callis can be reached at 360-417-3532 or at tom.callis@peninsuladailynews.com.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading