Lightning-caused electrical substation damage causes Port Angeles emergency, city says

PORT ANGELES — With winter just a few months away, an electrical transformer at Second and Washington streets that was zapped by a lightning bolt in July must be repaired or replaced as soon as possible, the City Council will be told this week.

When five thunderstorms crept across the North Olympic Peninsula on July 12-13 — emitting lightning that produced an extended, crackling show for residents — one bolt struck a 69,000-volt city transmission line, knocking out the transformer and the entire substation near Civic Field.

That substation accounts for 14 percent of the system’s capacity, said Public Works & Utilities Director Glenn Cutler in a memo to the City Council

The substation is critical to providing power to northeast Port Angeles, including Olympic Medical Center and the city’s wastewater treatment plant, said Cutler, who is requesting the council take action before the peak season begins in November.

The seven council members will be asked to approve a resolution that ratifies a declaration of emergency signed July 26 by interim City Manager Dan McKeen regarding the substation’s failure.

The meeting is at 6 p.m. in the council chambers at City Hall, 321 E. Fifth St.

A lightning bolt knocked out electrical power for a little more than an hour to 900 customers in the early morning of July 13.

Electricity was quickly routed from other city substations to customers served by the Second and Washington streets substation, Cutler said.

But the transformer remains out of commission and it could take six to 18 months to repair or replace it, Cutler said.

Electrical loads start increasing in November, with the advent of cold weather and greater use of electricity to heat homes and businesses.

“Can we carry loads during the winter without this? Yes, we could, but it becomes less of a margin of comfort level,” Cutler said.

A severe winter could leave the system with little spare capacity, he said.

No one is without power now, city staff members say.

But that could change.

The transformer should be repaired “as soon as possible,” says a proposed resolution declaring a state of emergency that the council will be asked to ratify Tuesday.

“Power has temporarily been rerouted, but there are now single points of failure,” it says.

“Should something else fail, there could be long-term outages.”

Cutler said council approval of the declaration of emergency will allow Public Works & Utilities to expedite the repair or replacement of the transformer, though “it may not be repairable,” according to the proposed resolution.

A declaration of emergency “basically suspends the traditional method of contracting,” Cutler said, estimating the project could cost $600,000 to $900,000.

Under an emergency, contracts for the project could be signed and obligations incurred without competitive bidding, publication of notices and provisions pertaining to the performance of public work, according to the declaration signed by McKeen.

Contracts exceeding $25,000 still will require council approval.

The transformer is 35 years old, making it difficult to find parts for repair, Cutler said.

In addition, most of the industry has moved to a higher kilovolt rating than the rating of the damaged transformer, according to the resolution.

“In a way, it’s almost a situation where in a few years, we’d be looking at actually replacing that thing,” Cutler said.

“It’s on the back end of its useful life.”

Transformers must be manufactured practically from scratch, Cutler said.

“They’ve got to build it, got to manufacture it, you’ve got to tell them the size, the configuration, the voltage,” Cutler said.

“It’s not a standard thing where you can call up the Chevy guy and say, ‘I need an alternator to go in the car,’ or ‘I need a new engine.’ It’s not just waiting there to be purchased.”

A transformer takes high voltage transmitted by the Bonneville Power Administration and “steps it down” to lower voltage for distribution to city residents and other customers, Cutler said.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 5060, or at paul.gottlieb@peninsuladailynews.com.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading