How bad is the gateway problem? Meeting this week to study crack in support wall

PORT ANGELES — Key parties in the design and construction of The Gateway transit center will study cracking in a foundation wall this week to determine how long the multimillion-dollar project remains on hold.

The financial implications of recent delays in construction of The Gateway are yet to be known, said Glenn Cutler, Port Angeles city public works director.

Completion of the project is on hold while engineers determine if cracking in the eastern foundation wall of the pavilion means that the structure, which is the roof of a parking garage, can’t support a planned second pour of concrete.

Cutler said on Friday that he is “cautiously optimistic” that the project will be completed in early- to mid-December.

The project, which began in June 2007, was expected to be completed this month. Its initial completion date was early September.

Cutler said the project at this time remains within its $14.7 million budget, which includes a contingency fund for cost overruns.

The Gateway is a joint project between the city of Port Angeles and Clallam Transit, which has $8.16 million in state and federal grant funding.

Design features

It includes a bus stop, parking garage, a pavilion, a four-faced clock tower, a break room for bus drivers, an office for downtown police officers and rest rooms.

The Gateway is located between Front and First streets and Lincoln and Laurel streets in downtown Port Angeles.

At their monthly meeting Thursday, representatives from the city of Port Angeles, Clallam Transit, Krei Architecture and Primo Construction are expected to determine if the cracking represents a structural problem.

Cutler said he will have a better idea of how this delay will affect the cost of the project after next week.

“I don’t know what, if anything, will be the financial impacts on the project,” he said.

“I don’t want to speculate either.”

Cutler said Krei, which is responsible for the design of The Gateway, has told the city that the cracking will not be a problem, but the city is using its own staff and engineering consultants to confirm it.

“They indicated to us that it is acceptable, and we can continue to work,” he said.

“But we don’t just accept that as, it’s OK. We are doing our due diligence to verify. It’s almost like a peer review.”

Cutler said the city consults with the engineering firm Zenovic and Associates in Port Angeles on these issues.

If a structural problem is discovered, Cutler said he couldn’t estimate how long the project would take to complete.

Process

The cracking occurred as a result of a technique known as “post tensioning” that is used in the horizontal concrete beam that supports the pavilion over parking spaces underneath, he said.

Steel wires within the concrete are pulled taunt, which gives the structure more support.

Cutler said this allows the structure to span a larger area and support more weight.

“Cracking is not unusual in this case,” he said.

Cutler said that about everything has been completed, except for the second pour of concrete on the pavilion floor.

The last pour will provide a slope for water drainage and a pattern for the pavilion floor.

Cutler said that poor weather shouldn’t delay pouring the concrete, as long as it doesn’t rain too hard.

In August, the City Council approved paying Krei an additional $90,960 for continuing its design and architectural review services during the delays.

________

Reporter Tom Callis can be reached at 360-417-3532 or tom.callis@peninsuladailynews.com.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading