Hood Canal Bridge’s first 1,000-ton anchor take the plunge

The first of 20 1,000-ton anchors was placed near the Hood Canal Bridge’s eastern half Tuesday, a job that took more than four hours.

“They finally got it to the bottom and they got it right where they needed it to be,” said Becky Hixson, bridge project communications manager for the state Department of Transportation.

The operation began at about 10:45 a.m. and was finished at about 2:45 p.m.

Hood Canal Bridge remains open while the anchors are being placed.

The floating bridge, which connects Jefferson and Kitsap counties, supports thousands of vehicles moving between the North Olympic and Kitsap peninsulas each day.

The bridge will be closed for six weeks in May and June 2009 for replacement of the aging, crumbling eastern half.

A western-half retrofit is scheduled for completion in 2010.

The first anchor was placed nearest the shoreline on the north Kitsap County end of the bridge, about 500 feet north of the bridge.

It was placed in the most shallow depth – 71 feet, Hixson said.

Other anchors will be placed as deep as 300 feet.

The DB Pacific, a large barge that can hold 2,000 tons and has a custom truss section, dropped the anchor.

Dropping the anchor involved pumping water into it to make it descend gradually.

“Three different types of sensors were used, telling if the anchor is facing bridge, if it’s level and if it’s in the right place on the ground,” Hixson explained.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading