Hood Canal Bridge closure dates changed

State axes plan to stop vehicular traffic for four straight weekends

The state Department of Transportation plans nighttime and weekend closures in May, June and September to take the place of weekend-long closures initially slated for August and September. (Peninsula Daily News file)

The state Department of Transportation plans nighttime and weekend closures in May, June and September to take the place of weekend-long closures initially slated for August and September. (Peninsula Daily News file)

SHINE — The state Department of Transportation has shelved plans to close the Hood Canal Bridge for four consecutive weekends in August and September and has replaced that schedule with one featuring weeknight and weekend nighttime bridge closures in May, June and September.

The tentative closure dates and times for the Hood Canal Bridge were announced Monday as DOT officials appeared to heed warnings from North Olympic Peninsula residents and government officials that their original proposal would be catastrophic to the area’s economy.

“The new dates strike the best balance between securing critical materials needed to make repairs to the bridge and installing those materials during calm weather when traffic volumes are lower,” said MaryLou Shannon, assistant region administrator of construction, in a press release.

Instead of four long-term weekend closures of the bridge, DOT made the decision to separate the work into three phases, she said.

“While this will result in more overnight closures of the bridge, it also allows the contractor to begin making the repairs in late spring and early summer — when weather conditions are typically more favorable — and keeps the closure hours more manageable for residents and visitors alike,” Shannon said.

Government and tourism officials in both Clallam and Jefferson counties had lobbied DOT hard not to close the bridge between Jefferson and Kitsap counties during summer weekends because of its effect on tourism.

Clallam County Commissioner Mike French wrote in a Monday afternoon email: “First off, we on the Olympic Peninsula value our transportation infrastructure and want to support WSDOT’s efforts to keep the Hood Canal Bridge in good working order.

“Secondly, I appreciate the efforts of the Olympic Peninsula Tourism Commission and the Olympic Peninsula Visitor’s Bureau (among others) to create strong communication lines between WSDOT Regional Administrator Steve Roark and all the various Olympic Peninsula partners (not just in the tourism industry).”

French noted that a lot of work remains to ensure visitors understand and plan around the closures this summer and fall.

“It’s encouraging that WSDOT listened carefully and respectfully to our concerns and adjusted their schedule accordingly, and I thank (Steve Roark, DOT Olympic Region Administrator) for being so generous with his time over the past few months as he discussed this and other important transportation projects in our region,” the email said.

Jefferson County Commissioner Kate Dean wrote in a Monday afternoon email: “This is great news for Jefferson County, businesses, and residents.

“We are really grateful to WSDOT for listening to our concerns and finding a less impactful solution. It’s still going to require careful planning, especially for emergency response, but we are prepared to work in short order with all the required partners to get ’er done!”

The work in May and June will focus on restoring the pyramids on the bridge that help guide the two halves of the bridge together. The repairs will require the use of boats and cranes in the water with the draw span open.

Emergency response access across the bridge will not be available during the overnight closures in May and June.

In September, workers will update the mechanism that securely connects both halves of the bridge and install new shock absorbers.

The center locks allow the bridge to be opened and closed and the state is obligated to open the bridge for marine traffic, including Navy ships. They guide the span and keep both halves of the bridge connected.

Work on these weather-sensitive systems won’t begin until Sept. 10, and it may include both weekday and weekend nighttime closures. DOT will announce the dates and times for that work later this summer.

This work requires calm weather, so all dates are subject to change, DOT said.

Travelers can get information about the Hood Canal Bridge via DOT email alerts, the DOT app and blog, and on the statewide travel map and DOT regional Twitter feed.

________

Reporter Brian Gawley can be reached at 360-452-2345, ext. 55650, or at brian.gawley@soundpublishing.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading