Hitch in Hood Canal Bridge project, state Transportation says; west-half hydraulic system worries continue

  • State Department of Transportation news release
  • Thursday, February 25, 2010 1:42pm
  • News

State Department of Transportation news release

SHINE – WSDOT is delaying the completion of the SR 104 Hood Canal Bridge project after functional testing of the bridge revealed poor performance of the west-half lift span hydraulic system.

“While conducting functional testing of the hydraulic systems we were able to identify this issue before it became an operational problem,” said Kevin Dayton, WSDOT region administrator. “Unfortunately, this testing phase has also caused unplanned and unexpected delays for travelers. We appreciate the community’s continued patience as we work to solve the draw span problem.”

Engineers are trying to determine why the rear hydraulic lifts of all three structures that make up the west-half draw span are operating slower than the front lifts. The systems are producing different pressures, which are causing the lift spans to operate at different speeds. Final testing work by contractor Kiewit-General was scheduled to wrap up by the end of February.

The Hood Canal Bridge’s west half was widened in 2006 with retrofit work on the lift systems occurring in 2009. The entire east half was replaced in May-June 2009 and continues to operate and open for marine vessels while the west-half retrofit continues.

Until the cause of the hydraulic issue is identified, most of the draw span testing – which requires closing the bridge to vehicle traffic – will be suspended although drivers may experience sporadic, daytime diagnostic test openings of up to 10 minutes, and continued weeknight test openings of up to 90 minutes between 10 p.m. and 4 a.m. WSDOT will provide at least 24 hours notice prior to nighttime closures. Whenever possible and to reduce the impact on motorists, these openings will be timed to occur during marine vessel openings.

Once the hydraulic issue is resolved, WSDOT estimates that functional testing will take about six nights of up to 90-minute closures between 10 p.m. and 4 a.m. to complete. West-half functional testing is approximately 50 percent finished, and will be followed by about three nights of tests of both the east and west draw spans. When functional testing and operational retrofitting work is complete, construction work on the bridge will conclude.

In May, crews from WSDOT’s Bridge Preservation Office will conduct federally-required annual inspections on the Hood Canal Bridge. The inspections, which include a total review of all systems, are standard for all moveable bridges in Washington and will require approximately three weeks of short-duration daytime and nighttime openings.

For more information, visit www.HoodCanalBridge.com

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading