Highway 101 work on schedule to be finished next fall

Project to replace five culverts

PORT ANGELES — Bridge construction on U.S. Highway 101 east of Port Angeles is on budget and on schedule to be completed next fall, a state Department of Transportation official said.

The $35.6 million project will replace five defective fish culverts with two full-span bridges or larger concrete-box culverts to improve fish migration in Bagley and Siebert creeks and their tributaries.

“It’s a huge benefit for salmon restoration,” WSDOT spokeswoman Tina Werner said in a Wednesday interview.

“The potential habitat gain for the fish is estimated at 41 miles, so this will be a big environmental win.”

The two-year project is part of WSDOT’s ongoing effort to improve fish passage under state or federal highways. Bagley and Siebert creeks support chinook and coho salmon, steelhead and bull trout.

Scarsella Brothers, Inc. of Kent, WSDOT’s primary contractor, broke ground on the project in May.

Highway traffic will continue to be funneled into one lane at the creeks until the work is complete. The temporary 45 mph speed limit will remain in effect though next fall.

“We’re very appreciative of the public’s patience, and we’re excited that work has progressed well,” Werner said.

There were 23 collisions investigated on U.S. Highway 101 through the four-mile construction zone from April 1 though Thursday, down from 24 during the same period in 2019, according to State Patrol statistics.

There had been 544 speed violations issued the project area since April 1, down from 667 during the same dates in 2019.

“We appreciate the cooperation of the motorists who have adhered to the temporary speed reduction within the active construction zone throughout the project,” said Trooper Chelsea Hodgson, State Patrol spokeswoman.

“Troopers have patrolled the area during the project to make sure both those who are driving through, as well as the crews working the project, are safe.”

“We can never stress enough for drivers to always slow down and pay extra attention in those areas for a variety of reasons,” Hodgson added. “Traffic patterns are often changed, lanes are narrowed and crews are actively working alongside flowing traffic.”

WSDOT is under a 2013 federal court injunction to remove state-owned culverts that impede salmon migration in much of Western Washington by 2030.

Werner said the existing culverts have “significant barriers” related to water velocity.

“We try to bundle many of these barriers in one contract to reduce construction fatigue for drivers so that we’re not having to come back year after year after year,” Werner said in a telephone interview.

Crews this week were working on abutment walls and foundations for the western half of the Bagley Creek bridge. Girders for the bridge are scheduled to be delivered during the second week of November, Werner said.

Three miles to the east, crews were wrapping up soil stabilization work along Siebert Creek.

“They’re going to continue work through the winter,” Werner said.

“Our crews will be able to maintain current travel flow, which is a single lane in each direction.”

The project was designed to maintain traffic flow on U.S. Highway 101. Drivers may encounter brief, intermittent closures when the bridge girders are delivered, Werner said.

In-water work will take place next summer during an eight-week fish window.

“At that time, Siebert (Creek) bridge will be up and the retaining walls will be done,” Werner said.

“That’s when our crews will go in, and they’re going to remove the old, outdated culverts. They’ll be removing those and doing a lot of stream-bed restoration with our biology teams.”

Updates on the Bagley and Siebert Creek fish barrier replacements will be posted on the WSDOT website, wsdot.wa.gov.

“This is a huge restoration project for DOT, and we are doing everything we can to make sure that the contractor stays on schedule, and we’re looking forward to having this project wrapped up next fall,” Werner said.

“We appreciate everyone’s patience.”

________

Reporter Rob Ollikainen can be reached at rollikainen@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading