Gravel pit project withdrawn

Applicant: Threats to family led to decision

SEQUIM — A Sequim applicant for a permit for a proposed gravel pit in Happy Valley has withdrawn his application, citing threats and even shots fired.

After the project was withdrawn Wednesday, a Thursday hearing before the Clallam County hearing examiner to consider the 4.74-acre basalt mine called Happy Valley Pit LLC was canceled.

John David Kirner, co-manager of Kirner Family Real Estate LLC No. 2, wrote building officials that his family “expected to encounter some opposition … and to honorably defend our actions and convictions. We fully expected to be rational with irrational individuals. We fully expected to come to a middle ground.”

However, they did not expect “extreme public defamation of our family’s character, and threats to our family’s way of life,” he wrote.

According to Clallam County records, the project on the west side of Happy Valley Road and Johnson Creek, aimed to extract about 214,000 cubic yards of material over five years. A single-family home was likely to be placed on the site once the mining was finished.

The operation would have been worked from 7 a.m. to 5 p.m. Monday through Friday with rock blasting proposed once per month, rock crushing on site about two days a week, and approximately 32 to 64 truck trips in and out per day as the site progressed, according to an August letter from project engineer Tracy Gudgel with Zenovic & Associates Inc. of Port Angeles.

The conditional use permit application was submitted by Kirner on Feb. 2, and in his letter rescinding the permit on Wednesday, he wrote his “family has owned and mined this land for decades, and we had hoped to sustain that legacy.”

He wrote that he had had threats of boycott of his business, anonymous threatening letters to his family’s home and threats against his family’s lives.

“Shots were fired from the public roadway into items upon my own home’s property, less than a few hundred feet of my front door,” Kirner wrote.

“This action was taken within hours after an article was aired on regional news channels about the application for the conditional use permit.”

He added, “the application for the conditional use permit was intended to continue to utilize the resources of our family land, consistent with the homesteading history of our community and land use in Clallam County.

“We never expected to receive these types of threats to our reputations and our lives.”

Residents’ responses

Kirner’s proposed project led neighbors to organize over many concerns, including traffic, noise and environmental impacts.

They conducted a meeting on July 30 that was attended by more than 100 residents, including Clallam County Commissioner Mark Ozias, and some formed the website stopthehappyvalleypit.org.

County building staff report they received nearly 200 letters concerned about the project prior to the planned public hearing about noise, dust, traffic and general opposition.

Diana Adamson, a spokesperson for Friends of Happy Valley, a coalition of area residents opposed to the project, wrote in a press release they “are thrilled that the application has been withdrawn (and) this proposal would have resulted in so many negative impacts, including impacts on traffic, dust, water wells, noise, and potential dangers to the environment of both humans and wildlife.”

As for the threats Kirner wrote about, Bryan Telegin, Friends of Happy Valley counsel, said the group “wishes to make known that they do not in any way condone threats, intimidation, defamation, or violence” toward Kirner and his family.”

“We wish him and his family well and hope they never experience such bad acts, now or in the future,” Telegin wrote.

Jamie and Bill Goodwin of Bell Hill wrote that “the mine is not consistent and appropriate within the character of the valley neighborhoods.”

“The mine has been closed for nearly 40 years (and) in those years that followed, hundreds of families moved into the valley and around Bell Hill,” they wrote. “The character of the valley was rural, farming and had no large housing developments 40 years ago. That is just not true today.”

Sheryl Greer of Happy Valley Road requested an environmental impact assessment, and traffic study for interconnected roads to the project.

“In just five short years, it has become exceptionally hazardous getting onto 101 from Happy Valley and turning right onto Happy Valley from (U.S. Highway 101),” she wrote.

“Happy Valley is narrow, has no walkway, no bike lame, and a ditch for much of the road.

“This road is not a location for large trucks to be on safely.”

Avonlea Lawrence of Happy Valley Road shared her concerns for animals, noise, and air pollution.

“The noise, blasting at 7 am., I would not like to wake up to that,” she wrote.

“And going on bike rides I won’t be safe anymore. The dust pollution will be very unsafe, too, especially for people who have allergies and the animals.”

Principal Planner Donella Clark in her Aug. 30 staff report recommended denying the project, writing that it conflicts with the county’s Comprehensive Plan and the area’s residential designation.

“Though mining is an important resource in Clallam County, the size and location of the proposal does not appear to be an ideal location for a mining operation, especially with the need for crushing and blasting in such proximity to residential development,” she wrote, citing noise and traffic concerns.

Clark reported that one residence was within 600 feet of the proposed property, and with nearby residences at a greater density of one dwelling per 5.1 acres, the project wouldn’t be designated as mineral resource lands without a noise study.

“Historically, the development pattern in the Happy Valley area is residential, with Bell Hill exceeding the density of typical rural development,” Clark wrote.

She added that “there are no known measures that will eliminate or even reduce (operational sounds, in particular blasting, rock crushing and heavy equipment operations) to a level compatible with the existing residential character of this area.”

“The slopes of Bell Hill further reduce the effectiveness of vegetative buffering thereby suggesting that reasonable noise attenuation to an acceptable level is not possible,” she wrote.

“Therefore the conversion of this property as proposed would be in conflict with the policies of the Comprehensive Plan and the character of the neighborhood.”

A Determination of Non-Significance (DNS) under the State Environmental Policy Act (SEPA) was issued with no significant adverse impacts to the area but Clark in her review would have required a 150-foot buffer from Johnson Creek rather than the classified 100 feet, and a habitat and wildlife survey to be reviewed by the Department of Fish and Wildlife.

In its project response, Fish and Wildlife staff wrote that there “does not appear to be potential impacts to wildlife species or habitats have been fully considered” with habitats and species records showing the presence of Roosevelt elk, little brown bat, yuma myotis, residential coastal cutthroat and trumpeter swans in winter.

Jamestown S’Klallam Tribal staff requested a 170 foot stream buffer to better accommodate the Sequim elk herd as they “lack a safe migration corridor due to continued development and Highway 101 and limits the herds ability to migrate and maintain healthy population.”

________

Matthew Nash is a reporter with the Olympic Peninsula News Group, which is composed of Sound Publishing newspapers Peninsula Daily News, Sequim Gazette and Forks Forum. Reach him at mnash@sequimgazette.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading