Gateway center could be open by Christmas

PORT ANGELES — The city of Port Angeles’ contract with Primo Construction for The Gateway will likely have to be extended to finish the project, said Glenn Cutler, city Public Works director, says.

“I anticipate it will be extended,” Cutler said Friday.

“I’m still cautiously optimistic it will be finished, and will be available for Christmas.”

The contract with Primo is for $8 million.

The project, which was estimated to cost $13.8 million, is budgeted at $14.7 million.

The budget includes a contingency fund for cost overruns.

Yvonne Ziomkowski, city finance director, said costs are a little over the initial estimate, but the city still has money to spend within that budget.

Ziomkowski said she won’t know the exact cost of the project until it is finished.

Cutler said that he did not know how much the extension would add to the construction contract’s portion of the cost of the project, because city staff members haven’t completed estimates.

He said he will find out early this week when Primo can begin finishing the project — if city staff confirm that there are no structural problems with The Gateway.

Cracking

The project has been delayed while cracking in the east foundation wall of The Gateway’s pavilion is analyzed.

A report from structural engineers sub-contracted by Krei Architecture shows The Gateway project to be structurally sound, Cutler said.

City staff and the engineering firm Zenovic and Associates of Port Angeles will review the report — which was presented during a meeting with representatives from the city and Clallam Transit, Krei, and Primo Construction — early next week to confirm its findings.

Terry Weed, Clallam Transit general manager, said the construction contract with Primo was for 18 months and began in June 2007.

Weed and Cutler said on Friday they did not remember which specific date the contract will end.

Cutler said the last major part of the construction still to be completed is a second layer of cement pouring on the pavilion, which will allow for water drainage.

The cement pouring has been on hold while the cracking is investigated.

Cutler said it was the pattern of cracking, “which radiated out from under a beam,” that caused concern.

In order to see what was occurring underneath, Cutler said the cracked cement was chipped away.

Weed said the cracking has delayed that aspect of the project from being completed for four to six weeks.

The Gateway, which is a joint city and Clallam Transit project, includes a bus stop, parking garage, a pavilion, a four-faced clock tower, a break room for bus drivers, an office for downtown police officers and rest rooms.

It was initially expected to be completed in September, but its most recent completion date was for earlier this month.

The city has received $8.1 million in state and federal grant funding, and Ziomkowski said it has applied for an additional $2.7 million from the state.

Tom Ellis, Exceltech construction inspector, said the parking area below the pavilion had some minor water leaks, which had been fixed. He said the water did not cause any damage.

Exceltech is responsible for project planning and management, Cutler said.

Gap not a problem

On the east side of The Gateway, a gap can be seen between the cement wall that aligns with the pavilion foundation.

Cutler said it occurred about a year ago when the wall settled in the soil below, and added it does not reflect a structural problem.

A metal plate may be used to fill in the gap, he said.

According to Ziomkowski, major costs for The Gateway include:

• About $8 million to Primo.

• About $3 million for property acquisition, done by Clallam Transit.

• $616,000 to Exceltech.

• $412,728 Krei contract, which includes design review during construction.

• About $200,000 for signs for The Gateway.

Clallam Transit has provided $500,000 toward the project, in addition to the money for acquiring property.

________

Reporter Tom Callis can be reached at 360-417-3532 or tom.callis@peninsuladailynews.com.

More in News

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas and Sue Authur, and Main Street employees, Sasha Landes, on the ladder, and marketing director Eryn Smith, spend a rainy morning decorating the community Christmas tree at the Haller Fountain on Wednesday. The tree will be lit at 4 p.m. Saturday following Santa’s arrival by the Kiwanis choo choo train. (Steve Mullensky/for Peninsula Daily News)
Decoration preparation

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas… Continue reading

Port Angeles approves balanced $200M budget

City investing in savings for capital projects

Olympic Medical Center Board President Ann Henninger, left, recognizes commissioner Jean Hordyk on Wednesday as she steps down after 30 years on the board. Hordyk, who was first elected in 1995, was honored during the meeting. (Paula Hunt/Peninsula Daily News)
OMC Commissioners to start recording meetings

Video, audio to be available online

Jefferson PUD plans to keep Sims Way project overhead

Cost significantly reduced in joint effort with port, city

Committee members sought for ‘For’ and ‘Against’ statements

The Clallam County commissioners are seeking county residents to… Continue reading

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on Saturday at the Airport Garden Center in Port Angeles. All proceeds from the event were donated to the Peninsula Friends of Animals. (Dave Logan/for Peninsula Daily News)
Santa Paws

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on… Continue reading

Peninsula lawmakers await budget

Gov. Ferguson to release supplemental plan this month

Clallam County looks to pass deficit budget

Agency sees about 7 percent rise over 2025 in expenditures

Officer testifies bullet lodged in car’s pillar

Witness says she heard gunfire at Port Angeles park

A copper rockfish caught as part of a state Department of Fish and Wildlife study in 2017. The distended eyes resulted from a pressure change as the fish was pulled up from a depth of 250 feet. (David B. Williams)
Author to highlight history of Puget Sound

Talk at PT Library to cover naming, battles, tribes

Vern Frykholm, who has made more than 500 appearances as George Washington since 2012, visits with Dave Spencer. Frykholm and 10 members of the New Dungeness Chapter, NSDAR, visited with about 30 veterans on Nov. 8, just ahead of Veterans Day. (New Dungeness Chapter DAR)
New Dungeness DAR visits veterans at senior facilities

Members of the New Dungeness Chapter, National Society Daughters of… Continue reading

Festival of Trees contest.
Contest: Vote for your favorite tree online

Olympic Medical Center Foundation’s Festival of Trees event goes through Dec. 25