Forks Library renovation pushed $12,000 over budget by change orders

FORKS — The renovation of the roughly 40-year-old Forks Library produced a bevy of surprises during the eight-month construction project resulting in the work costing about $12,000 more than expected, according to a North Olympic Library System staff report.

“Probably the most surprising thing was the number and variety of them,” System Director Paula Barnes said, referring to the 27 change orders needed for the $847,232 project.

The entire renovation project for the library at 171 S. Forks Ave, from design to construction, was originally budgeted at $835,000, putting the actual cost about 1.5 percent over budget.

“When all is said and done, [it’s] not terribly bad,” Barnes told the library system’s board of trustees at Thursday’s meeting.

The cost overruns stemmed mainly from unanticipated findings as renovation work progressed, Barnes said.

These included fixing unexpected dry rot, replacing more electrical wiring then originally planned and replacing windows along the west side of the building that were all unexpectedly different sizes, Barnes explained.

“They all turned out to be slightly different sizes, so all the trim had to be sort of on a custom basis, window by window,” Barnes said.

“One would think that a long row of windows would be the same size.”

Barnes said she made a critical error in only putting aside 5 percent of the project budget as a contingency fund when industry standard calls for at least 10 percent on renovations of old buildings.

“We thought we had done such a thorough review of the building that a way to keep costs down was to go for a 5 percent contingency, which is fairly common for a new building,” Barnes said.

“We really should have gone with the 10 percent.”

The focus of the renovation was a new roof, new conference room and new technology, including an express-checkout station.

The overhaul also updated the building’s heating/ventilation system, added new wall and floor coverings, renovated restrooms, updated a meeting room and insulated windows.

Library system funds paid for $672,263 of the project, Barnes said, with a community fundraising campaign raising most of the remaining cost.

Forks Branch Manager Theresa Tetreau said the remodel was sorely needed and has made the Forks Library more attractive to people simply wanting to come and read quietly.

“And we’re actually seeing that more since the remodel, just because it’s a warm and comfortable place to be,” Tetreau said.

Tetreau said comments about the changes have been overwhelmingly positive.

“It’s all just very Forks,” Tetreau said. “People come in and are just gushing about it.”

Barnes said she considers the renovation a success.

“Even though there were some bumps in the road, we were all very satisfied at the end, especially the library users, and that’s what it’s all about,” Barnes said.

The library’s regular hours are from 10 a.m. to 7 p.m. Mondays through Thursdays and from 10 a.m. to 6 p.m. Fridays and Saturdays.

For more information, phone the library at 360-374-6402, email Forks@nols.org or visit www.nols.org.

The library system also manages branches in Clallam Bay, Port Angeles and Sequim.

________

Reporter Jeremy Schwartz can be reached at 360-452-2345, ext. 5074, or at jschwartz@peninsuladailynews.com.

More in News

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas and Sue Authur, and Main Street employees, Sasha Landes, on the ladder, and marketing director Eryn Smith, spend a rainy morning decorating the community Christmas tree at the Haller Fountain on Wednesday. The tree will be lit at 4 p.m. Saturday following Santa’s arrival by the Kiwanis choo choo train. (Steve Mullensky/for Peninsula Daily News)
Decoration preparation

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas… Continue reading

Port Angeles approves balanced $200M budget

City investing in savings for capital projects

Olympic Medical Center Board President Ann Henninger, left, recognizes commissioner Jean Hordyk on Wednesday as she steps down after 30 years on the board. Hordyk, who was first elected in 1995, was honored during the meeting. (Paula Hunt/Peninsula Daily News)
OMC Commissioners to start recording meetings

Video, audio to be available online

Jefferson PUD plans to keep Sims Way project overhead

Cost significantly reduced in joint effort with port, city

Committee members sought for ‘For’ and ‘Against’ statements

The Clallam County commissioners are seeking county residents to… Continue reading

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on Saturday at the Airport Garden Center in Port Angeles. All proceeds from the event were donated to the Peninsula Friends of Animals. (Dave Logan/for Peninsula Daily News)
Santa Paws

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on… Continue reading

Peninsula lawmakers await budget

Gov. Ferguson to release supplemental plan this month

Clallam County looks to pass deficit budget

Agency sees about 7 percent rise over 2025 in expenditures

Officer testifies bullet lodged in car’s pillar

Witness says she heard gunfire at Port Angeles park

A copper rockfish caught as part of a state Department of Fish and Wildlife study in 2017. The distended eyes resulted from a pressure change as the fish was pulled up from a depth of 250 feet. (David B. Williams)
Author to highlight history of Puget Sound

Talk at PT Library to cover naming, battles, tribes

Vern Frykholm, who has made more than 500 appearances as George Washington since 2012, visits with Dave Spencer. Frykholm and 10 members of the New Dungeness Chapter, NSDAR, visited with about 30 veterans on Nov. 8, just ahead of Veterans Day. (New Dungeness Chapter DAR)
New Dungeness DAR visits veterans at senior facilities

Members of the New Dungeness Chapter, National Society Daughters of… Continue reading

Festival of Trees contest.
Contest: Vote for your favorite tree online

Olympic Medical Center Foundation’s Festival of Trees event goes through Dec. 25