Five capital projects proposed for Fort Worden campus

Emergency generator made a priority after large-scale power outage last month

PORT TOWNSEND — Recent power outages at the Fort Worden campus prompted the Fort Worden Public Development Authority’s Coordinating Committee to add the purchase of an emergency generator to its list of five capital projects proposed to Washington State Parks for capital project funding.

The Fort Worden Operations works group presented five capital projects for approval by the coordinating committee on Dec. 6. The panel is to present the projects to Washington State Parks for review and potential funding.

A lease agreement with Washington State Parks that was signed in 2013 set up the structure for the public development authority’s management of the campus portions of the 434-acre park — about one-fourth of the park and including most of the buildings — while State Parks continues to manage the camping, beach and recreation areas.

The operations workgroup has presented these projects in the past; at this meeting, the projects’ priority ranking were changed.

Still at the top of the list is the campus-wide replacement of the fire alarm system, which is outdated and failing, panel members said.

“We kept this as the top priority and have been working around the clock this week on issues related to this system,” said Aislinn Palmer, interim operations director.

That project is estimated to cost a maximum of $2.5 million.

Moved up in priority was the burying of powerlines across the Fort Worden campus. That includes the purchase of an emergency generator.

“This project was previously focused on the overhead electrical lines and a continuation of that project and then had as a sort of afterthought consideration of emergency generator capabilities,” Palmer said.

November’s massive power outage made it clear that the generator should be a higher priority, Palmer said.

The Jefferson County Public Utility District reported more than 11,000 without power at the peak of the Nov. 15 storm — “one of the biggest outage incidents we’ve had in years,” the PUD reported on its Twitter feed.

“It was a stark reminder of how vulnerable the power is here and what a big deal that is to everyone on campus when the power is out … It really just brought to light that a generator should be a high priority for this property,” Palmer said last week.

The estimated cost for the project is $1.5 million. The operations workgroup is seeking bids on the generator so the cost could increase.

The third project focuses on Building 298 on the Fort Worden campus.

Repairs are needed to the exterior of the building, specifically to the multi-level porches that wrap around the east and south sides of the building, Palmer said.

Leaks in the porches have led to water damage on the interior of the building.

The cost of the repairs is about $2 million, including assessments and designs for future renovations of the building.

The fourth project focuses on making the Fort Worden campus more accessible under Americans with Disabilities Act (ADA) guidelines by upgrading existing facilities.

“We all believe very strongly that ADA and other safety upgrades are needed at the campus,” Palmer said.

This project is estimated to cost $2.5 million.

“Some of our buildings might have ADA from the outside, but once you get inside the buildings are not ADA accessible, so that’s a little awkward; yes, you can get in but suddenly the building isn’t functional,” said Brian Hageman, Fort Worden Park manager.

Hageman noted that consideration may be given toward ramp usage rather than elevators.

“For example, the park ranger office and the administrative building,” Hageman said. “The lifts outside are not functioning and what we are finding it that elevators are very expensive and they require annual (Labor and Industries) inspections and maintenance, so we are kind of hoping to look at other ideas like ramps.”

The final proposed capital project is a multi-phased one addressing exterior design and construction improvements to buildings on Officers Row and World War II-era residences on the campus.

This project will cost an estimated $10.6 million. The PDA has asked for $2.6 million in funding from Washington State Parks.

“This work is moving very slowly and these are very big projects which makes them a high priority since this is one of the signature areas of the park and one of the highest attractions,” Palmer said.

________

Reporter Ken Park can be reached at kpark@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading