Firm racing toward deadline on Port Townsend jetty

Underwater work must be done by Jan. 31

PORT TOWNSEND — The company in charge of constructing the new south jetty at Point Hudson Marina is doubling the number of its crew and shifting to a round-the-clock schedule in order to complete underwater work on the project by the end of the month.

Orion Marine Group is racing to meet a Jan. 29 deadline set by federal and state agency biologists when all in-water work must end. The date is an extension of the original Jan. 15 end-of-work window intended to minimize the impact of construction on salmon and other marine species.

Orion decided to switch to a 24-hour schedule with two crews working six days a week on back-to-back 12-hour shifts last week. The change will not affect the cost of the project, Port of Port Townsend Executive Director Eron Berg said.

“The contractor agreed to complete a scope of work within a time period, so they have control of the site and control of the work week,” Berg said. “It’s really been up to them to decide how they want to perform the work.”

Berg said Orion was finished pile driving but still needed to mount the waling beams and tie rods that help keep the piles in place.

“It’s getting all the steel in and making it secure so they can put that 5,000 tons of rock in,” he said. “Then in the month of February they’ll be able to do anything above the ordinary high water mark.”

Orion began work in September immediately after the Wooden Boat Festival ended. Although the weather has been fairly cooperative, Berg said there were elements of the south jetty that made the project more challenging than the north jetty that was completed ahead of schedule last January.

“It’s physically longer, it’s in deeper water, and there was also prepping to move a bunch of unsuitable material and replacing it with thousands of tons of bedding and armourstone,” Berg said.

Orion also had to bring back an impact hammer to drive about a dozen piles when a hydraulic vibrator was unable to penetrate the shoreline.

Berg said he believed the noise would be minimal, although there have been no complaints so far from neighbors during construction.

After the in-water work window closes, Orion will focus on the above-water portions of the project, like constructing the pedestrian walkway. All work must be completed by March 1, when Point Hudson is scheduled to re-open to marine traffic.

The port plans to hold an event in April to celebrate completion of both the north and south jetty projects.

Funding for the $14 million Point Hudson jetty replacement comes from a combination of federal, state, county and the port’s Industrial Development District levy.

________

Reporter Paula Hunt can be reached at paula.hunt@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading