This week, Interwest Construction workers plan to complete underground utility work before moving onto sidewalk work along West Fir Street. (Matthew Nash/Olympic Peninsula News Group)

This week, Interwest Construction workers plan to complete underground utility work before moving onto sidewalk work along West Fir Street. (Matthew Nash/Olympic Peninsula News Group)

Fir Street rehab in full swing for school start in September

Superintendent seeks transportation plan by end of August

SEQUIM — Students, parents and Sequim School District staff can expect bumpy rides and more detours around the West Fir Street Rehabilitation Project after school resumes Sept. 4.

The $6.2 million project spanning Sequim Avenue to Fifth Avenue was started in May and will continue to impact nearby schools and homes through next summer, city of Sequim staff said.

Mary Budke, executive director of the Boys & Girls Clubs of the Olympic Peninsula, said her staff have been “excellently prepared for what was coming” with construction in front of the Carroll C. Kendall unit at 400 W. Fir St.

“But the reality is you never know how you’re going to get into work each morning,” Budke said.

“I feel worse for our parents than us working here. Where you drop off your kid in the morning could change in the afternoon.”

Rob Clark, interim superintendent, said after the School Board meeting Monday that district staff intend to share a plan with parents for student transportation — buses and drop-offs and pick-ups — by this coming Wednesday, Aug. 28.

Matt Klontz, Sequim city engineer, said Monday that Interwest Construction will focus on sidewalk work in front of the schools in September and October.

Temporary asphalt will be placed on the road after that, he said, with final pavement going down tentatively early next summer.

This week, construction crews will finish grounding utilities, Klontz said, adding that stormwater and irrigation leaks that caused flooding in prior years are expected to be repaired.

Klontz said utilities run to the former Sequim Community School site in preparation for potential expansions.

As for traversing Fir Street, city staff recommend using neighboring roads instead.

“We’re going to emphasize people use Alder Street to go east-west bound,” Klontz said in an interview. “It’s going to be much smoother and to turn into [Helen Haller Elementary or the Boys & Girls Clubs unit], use Third or Fourth Avenue.”

He told school officials Monday that North Second Avenue is mostly closed, but parents of Olympic Peninsula Academy students can park and go through the street as usual.

School Board director Jim Stoffer asked for a dry run for school buses so they can see how traveling goes. Clark agreed and said district staff will set it up prior to school starting.

Where pedestrians can walk hasn’t been announced yet, with “Sidewalks Closed” signs posted along the street.

Budke said in an interview she’s concerned about where club members will be able to walk, particularly when the weather is wet.

However, she said construction crews have kept her updated on projects, which club staff share with parents and guardians online and in person.

Budke said if people need to park, the club has ample parking on the west and north sides of its building after the field has been mowed.

Prior to school starting, Klontz said he wants to coordinate with all of the school district’s afternoon staff, who lead bus and vehicle pick-up.

Construction on the West Fir Street Rehabilitation Project began May 13 in an effort to provide new bike lanes, sidewalks on both sides of the road with Americans with Disabilities Act-compliant curbs and intersections, new underground utility connections, new piping for water, sewer, stormwater, irrigation and reused water, street lighting, street crossing enhancements and a new traffic signal at North Fifth Avenue and West Fir Street.

Klontz previously said the road has an has engineer-rated low pavement condition index of 26 out of 100 — considered one of the worst among city streets.

Residents can continue to sign up for updates online at www.sequimwa.gov by going to the “Notify Me” page and registering for Fir Street Construction under the Alert Center with options for email and text notifications.

For more information, call Sequim Public Works Department at 360-683-4908.

________

Matthew Nash is a reporter with the Olympic Peninsula News Group, which is composed of Sound Publishing newspapers Peninsula Daily News, Sequim Gazette and Forks Forum. Reach him at mnash@sequimgazette.com.

Reporter Conor Dowley contributed to this story.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading