Final cost of transit center in Port Angeles still unknown; parties remain in dispute over price related to crack repair

PORT ANGELES — It opened 22 months ago, but the final price tag for The Gateway transit center remains unknown.

The reason: Clallam Transit and Primo Construction have yet to settle a dispute over how much the Sequim company should be compensated for a change order prompted by a large crack in the facility’s foundation.

Attorneys representing Primo and Clallam Transit will meet with a mediator May 26 to attempt to reach an agreement.

Primo is seeking $179,976. Clallam Transit says it should be less.

“We have dramatic differences in what that value should be,” said transit General Manager Terry Weed, referring to the claim.

Transit has claim, too

Additionally, the countywide transit agency, which owns The Gateway, plans to file its own claim against another contractor once Primo’s claim is settled, Weed said.

Clallam Transit believes that contractor, Krei Architecture, is responsible for the design flaw that lead to the crack and that it owes the agency about $500,000 in related costs, he said.

The change-order cost is part of that $500,000.

Steve Aisaka, Krei risk management director, said he had no comment.

Primo staff couldn’t be reached for comment.

The Gateway — a joint venture between Clallam Transit and the city of Port Angeles located along Front Street, Lincoln Street and Railroad Avenue — opened in June 2009. It includes a transit lane, plaza and two parking garages.

Crack caused delay

Completion of the facility was delayed seven months while a large crack discovered the beneath the plaza was fixed.

The project had a budget of $14.7 million as it neared its completion — with $8.1 million in federal and state grants, $500,000 from Clallam Transit and $6.1 million from the city.

The last tally of the project’s cost was $15.4 million, with the city covering the additional cost, said city Finance Director Yvonne Ziomkowski.

That tally was made in October 2009, the last time the city received an invoice from Clallam Transit on the project, she said.

Since then, Clallam Transit has spent $6,835 on attorney fees related to the claim and resolving a lawsuit over property condemned for the project.

The city is required to cover any cost overruns for the project, according to an agreement between the project partners.

Weed said the city will be billed for the additional expenses.

Grant will help

But Glenn Cutler, city public works director, said it’s possible the city won’t have to spend another dime.

The Federal Transit Administration has awarded the project another $550,000 grant, he said.

However, when the project will receive the grant has not been determined.

“I think there’s a potential for some of the project to be paid money back,” Cutler said.

Craig Miller, Clallam Transit’s attorney, said the Primo claim will head to arbitration if no agreement on the change-order cost can be reached this month.

The arbitrator’s decision would be final, he said.

Weed said it’s unclear how much longer it will take for the claims to be resolved.

“Our attorney says that’s the way the system works,” he said.

________

Reporter Tom Callis can be reached at 360-417-3532 or at tom.callis@peninsuladailynews.com.

More in News

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas and Sue Authur, and Main Street employees, Sasha Landes, on the ladder, and marketing director Eryn Smith, spend a rainy morning decorating the community Christmas tree at the Haller Fountain on Wednesday. The tree will be lit at 4 p.m. Saturday following Santa’s arrival by the Kiwanis choo choo train. (Steve Mullensky/for Peninsula Daily News)
Decoration preparation

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas… Continue reading

Port Angeles approves balanced $200M budget

City investing in savings for capital projects

Olympic Medical Center Board President Ann Henninger, left, recognizes commissioner Jean Hordyk on Wednesday as she steps down after 30 years on the board. Hordyk, who was first elected in 1995, was honored during the meeting. (Paula Hunt/Peninsula Daily News)
OMC Commissioners to start recording meetings

Video, audio to be available online

Jefferson PUD plans to keep Sims Way project overhead

Cost significantly reduced in joint effort with port, city

Committee members sought for ‘For’ and ‘Against’ statements

The Clallam County commissioners are seeking county residents to… Continue reading

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on Saturday at the Airport Garden Center in Port Angeles. All proceeds from the event were donated to the Peninsula Friends of Animals. (Dave Logan/for Peninsula Daily News)
Santa Paws

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on… Continue reading

Peninsula lawmakers await budget

Gov. Ferguson to release supplemental plan this month

Clallam County looks to pass deficit budget

Agency sees about 7 percent rise over 2025 in expenditures

Officer testifies bullet lodged in car’s pillar

Witness says she heard gunfire at Port Angeles park

A copper rockfish caught as part of a state Department of Fish and Wildlife study in 2017. The distended eyes resulted from a pressure change as the fish was pulled up from a depth of 250 feet. (David B. Williams)
Author to highlight history of Puget Sound

Talk at PT Library to cover naming, battles, tribes

Vern Frykholm, who has made more than 500 appearances as George Washington since 2012, visits with Dave Spencer. Frykholm and 10 members of the New Dungeness Chapter, NSDAR, visited with about 30 veterans on Nov. 8, just ahead of Veterans Day. (New Dungeness Chapter DAR)
New Dungeness DAR visits veterans at senior facilities

Members of the New Dungeness Chapter, National Society Daughters of… Continue reading

Festival of Trees contest.
Contest: Vote for your favorite tree online

Olympic Medical Center Foundation’s Festival of Trees event goes through Dec. 25