Explosion brings down more of Glines Canyon Dam [ *** GALLERY *** ]

OLYMPIC NATIONAL PARK — An explosion took down about an additional 6 feet of Glines Canyon Dam last week, and at least one more explosion is expected next month.

Barnard Construction Company Inc. crews blew up a portion of the upper dam on the Elwha River on Thursday.

“We took out some of the concrete from the dam that we couldn’t get to with the barge on the far right-hand side [looking downstream],” said Brian Krohmer, project manager.

“The shoreline is too shallow for the barge, so we had to drill and blast it,” he said.

Glines Canyon Dam is now about 42 feet shorter than its original 210-foot height.

Barnard, a Bozeman, Mont.-based company contracted by Olympic National Park to remove both Glines Canyon Dam and the lower Elwha Dam, drilled holes for the explosives during snowstorms the week of Jan. 15.

Crews used a “man basket” to lower themselves to that section of the dam, Krohmer said.

At least one more explosion will be needed later on that side of the Glines Canyon Dam, Krohmer said.

Before that happens, crews will chisel another 3 feet or so off the top of the dam by midweek and then wait through a 14-day hold period designed to give the river time to erode the sediment in the Lake Mills delta.

Underwater pillars

During the hold period, Barnard crews will install two underwater pillars called “spud piles” on the front corners of the barge.

The piles will brace the barge against the face of the dam.

After the two-week hold period, “we’ll have at least one more blast on that side” of Glines Canyon Dam, Krohmer said, which will remove another 6- to 8-foot section.

“There’s so much rebar in the concrete next to the embankment that it’s difficult to drill,” he added.

“There are still a lot of unknowns there,” Krohmer said.

“There’s a lot of work left to do.”

The dam is expected to be completely demolished in early 2014.

“Glines is obviously going to take longer to complete than the Elwha Dam,” Krohmer said.

The Elwha Dam is expected to be completely removed by early 2013.

Work is much farther along there.

Some 44 feet remains to be removed from the lower dam, which was originally 108 feet tall, so it won’t be long before the visible part of the dam is taken down to the riverbed.

“What you can’t see is the work on the powerhouse,” Krohmer said.

“We’re still removing the substructure of that,” and that work should be finished by midweek, Krohmer said.

The river was diverted to the left channel late last week and will remain there for three to five weeks while crews finish removing the gravity dam.

Then, crews will begin moving some 67,000 cubic yards of dirt and rock that were fill material just upstream of the dam.

The material will be placed on the slope where the powerhouse and penstocks, the large metal pipes that led from the dam to the powerhouse, once stood.

Barnard Construction crews began in September chipping away at the two dams, built without fish ladders nearly a century ago, as part of a $325 million federal project to restore the river’s once-famous salmon runs.

The Elwha Dam was built in 1913 five miles from the mouth of the river, forming the now-disappeared Lake Aldwell, and the Glines Canyon Dam, which formed Lake Mills 14 miles upriver, followed in 1927.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading