Work continues Tuesday, Jan. 28, 2020, at the Shore Aquatic Center under construction in Port Angeles. (Keith Thorpe/Peninsula Daily News)

Work continues Tuesday, Jan. 28, 2020, at the Shore Aquatic Center under construction in Port Angeles. (Keith Thorpe/Peninsula Daily News)

Expanded Port Angeles pool set to reopen in June

Shore Aquatic Center ‘right on budget, right on time’

PORT ANGELES — Steve Burke gets the question all the time.

The Shore Aquatic Center is still scheduled to open in June, the pool’s executive director said Tuesday.

“I want to print up a shirt that says ‘We are still planning to open in June,’ ” said Burke, executive director of the Port Angeles pool.

“We’re right on budget, and we’re right on time. So sometime in June.”

The Port Angeles aquatic center formerly known as William Shore Memorial Pool has been closed since May 2019 for a $20 million renovation and 10,000 square-foot expansion.

After demolishing much of the old building last fall, crews have completed a steel frame for the new facility at the corner of Fifth and Lincoln streets.

Cross-laminated timber panels were being installed this week on sections of the roof, Burke told a Port Angeles Business Association audience.

The panels are made of three plies of hemlock and a single ply of fir.

“They just pick them right off of the semi truck and put them right on the roof,” Burke told about two dozen PABA members at their weekly breakfast meeting at Joshua’s Restaurant.

“We did that whole roof on the east side and the west side in a single day.”

The new aquatic center will have a lap pool, one-meter diving board, warm-water pool for exercise therapy and swim lessons, a children’s pool with a beach entry and a 10- to 12-person spa with 104-degree water.

The kids’ pool will have swirling splash features like a “lazy river” and “vortex ring.”

“We decided to do a lazy river instead of a slide because the lazy river actually can be used all day,” Burke said.

“A lot of seniors will use it during the day for resistance walking, to walk against the current, and then the kids use it as much as you give it to them.”

Burke said he expected at least a 30-percent spike in pool attendance when the facility reopens.

“When we shut down, we were averaging about 100,000 visits per year,” Burke said.

“So we increased quite a bit (from 23,000 annual visits in 2009). We’ll do a big jump on this one because there’s going to be things that have never been offered.”

The William Shore Memorial Pool District took ownership of the pool from the city of Port Angeles in 2009 after voters approved the new junior taxing district. City officials had considered closing the pool because of its age.

The expanded aquatic center will have a dedicated space for birthday parties and the Splash, Play and Active Recreation for Kids (SPARK) Squad after-school program.

“We’ll be able to house about 100 kids in our program,” Burke said.

“We get to teach 100 kids how to swim. That’s the whole goal.”

The pool is used by a swim club and the Port Angeles High School boys and girls swim teams, which moved to the Sequim YMCA for the 2019-2020 school year.

“The two entities that probably sacrificed the most is the swim club and the swim teams because we didn’t really have a good solution for them,” Burke said of the pool closure.

The pool at 225 E Fifth St. also is used by members of Coast Guard Air Station/Sector Field Office Port Angeles and patients from Olympic Medical Center, Burke said.

“It looks like we’ll actually have a physical therapist on site doing classes, and that will be part of the hospital partnership,” Burke said.

The new Shore Aquatic Center, shown Tuesday, Jan. 28, 2020, will feature a new entrance facing Lincoln Street in Port Angeles. (Keith Thorpe/Peninsula Daily News)

The new Shore Aquatic Center, shown Tuesday, Jan. 28, 2020, will feature a new entrance facing Lincoln Street in Port Angeles. (Keith Thorpe/Peninsula Daily News)

Burke displayed photographs of the construction during his 40-minute presentation.

Crews sprayed 70 cubic yards of shotcrete — sprayed concrete — to form the therapy pool in one day, Burke said.

The old pool basin was kept for the new aquatic center because “they build them exactly the same way,” Burke said.

The main entrance and locker rooms were moved from the east side of the building to the west. Much of the south side of the building will be covered by glass.

An average of 50 workers have been on site during construction, nearly all of whom live in Clallam County, Burke said. Neeley Construction of Puyallup is the primary contractor.

The pool will reopen in June with an estimated 80 employees. Most of those positions are part time.

“We’re the first job for a lot of kids, and so we get to teach them how to talk to a customer, how to answer the phone, how to take a message,” Burke said.

“Everybody leaves the pool,” he added. “If they don’t, we get to sit down and talk to them about their aspirations in life.”

Burke said the price of admission will remain low when the pool reopens — about $10 for a family to swim.

“We’re the cheapest entertainment in town,” Burke said.

“You can’t take your kids to a movie for 10 bucks. You can’t go bowling for 10 dollars.

“For me, if we price it so people can’t afford it, then we’ve kind of lost our whole mission statement,” Burke said.

Shore Aquatic Center is named for William “Bill” Shore, who taught thousands of Port Angeles children how to swim.

Burke said he spoke with members of the Shore family about the name change and invited them to the reopening in June.

“He was a high school swim coach and logger back in the ’50s,” Burke said.

“You couldn’t really do his technique for swim lessons anymore. Being a logger, his technique was throw them in, they’ll figure it out. We’re not really able to do that anymore.”

________

Reporter Rob Ollikainen can be reached at 360-452-2345, ext. 56450, or at rollikainen@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading