Shane Phillips of Mott MacDonald presents three alternatives to the Port of Port Townsend commissioners Wednesday, Feb. 12, 2020, during a port workshop. Phillips said construction could begin as early as winter 2021, provided all permitting can be secured by that time. (Brian McLean/Peninsula Daily News)

Shane Phillips of Mott MacDonald presents three alternatives to the Port of Port Townsend commissioners Wednesday, Feb. 12, 2020, during a port workshop. Phillips said construction could begin as early as winter 2021, provided all permitting can be secured by that time. (Brian McLean/Peninsula Daily News)

Engineering firm urges replacement of Point Hudson breakwater

Port of Port Townsend commissioners to consider proposal

PORT TOWNSEND — A preferred alternative to replace the south breakwater at Point Hudson could be under construction as early as winter 2021, an engineering firm said.

The proposal, presented Wednesday during a Port of Port Townsend commission workshop, would cost between $5.5 million and $6.5 million, and it would depend on timely permitting through the U.S. Army Corps of Engineers, according to a civil engineering firm based in Seattle.

Port commissioners still have to approve the project. They could discuss it as early as their next business meeting on Feb. 26.

Pilings and corroded cables sit inside the south breakwater at Point Hudson. A proposed replacement project would substitute steel pilings and smaller rocks, possibly tied down with the same types of casings that keep rocks from falling onto vehicles on mountain passes. (Brian McLean/Peninsula Daily News)

Pilings and corroded cables sit inside the south breakwater at Point Hudson. A proposed replacement project would substitute steel pilings and smaller rocks, possibly tied down with the same types of casings that keep rocks from falling onto vehicles on mountain passes. (Brian McLean/Peninsula Daily News)

Shane Phillips, the vice president and deputy coastal and ports practice leader for Mott MacDonald, told port commissioners the preferred alternative would replace the entire length of the existing south breakwater and replace it with new piles, rock and lagging in addition to a new timber walkway in the middle.

The south jetty replacement project has been ranked the top priority of the port’s capital projects since 2015.

Phillips presented three alternatives that ranged from encapsulating the existing structure to partial replacement with encapsulation in addition to full replacement.

The south and north breakwaters would be designed and permitted at the same time and likely would be constructed in phases, Phillips said.

He cautioned port commissioners about the permitting phase, saying the Corps has a large backlog of projects that could take between 18 and 36 months.

“It could be the winter of 2022 would be realistic for the first time you could get out there and work on the breakwater,” he said.

Pilings stacked at an angle hold a walkway atop the south breakwater at Point Hudson, although the walkway has been closed. The preferred alternative would be to replace the structure with steel pilings in a smaller footprint than what currently exists. (Brian McLean/Peninsula Daily News)

Pilings stacked at an angle hold a walkway atop the south breakwater at Point Hudson, although the walkway has been closed. The preferred alternative would be to replace the structure with steel pilings in a smaller footprint than what currently exists. (Brian McLean/Peninsula Daily News)

In addition to the corps, permitting would need to go through the National Marine Fisheries Service, Deputy Director Eric Toews said.

“I think putting our best foot forward early in the process is critical,” Toews said. “We want to have the best possible chance of having a self-mitigating project as possible.”

The breakwater replacement would be slightly smaller than the current footprint and would include the removal of creosote and other environmental impacts, Phillips said.

The proposal includes uncoated steel pipe piles, battered to match existing aesthetics, and the core would contain large, high-quality granite that likely would come from the Cascade mountains, Phillips said.

The piles would be taller than the existing structure to account for sea level rise, he added.

“Even at the height of the current structure, it’s still higher than Water Street,” Commissioner Bill Putney said.

In a preferred alternative presented Wednesday during a Port of Port Townsend workshop, a new timber walkway would replace the one that currently sits on top of the south breakwater. (Brian McLean/Peninsula Daily News)

In a preferred alternative presented Wednesday during a Port of Port Townsend workshop, a new timber walkway would replace the one that currently sits on top of the south breakwater. (Brian McLean/Peninsula Daily News)

The new structure would be built for a 30-year lifespan, Phillips added.

“The main thing is, you don’t want waves coming in and rolling right over the top of it,” he said. “If you have some over-topping, that’s acceptable because it wouldn’t affect the basin very much.”

The original structures were built by the military in 1934 and mostly used to offload supplies, Phillips said.

A major reconstruction took place in 1969 as it was converted to a small-craft harbor.

“The primary purpose is to protect the infrastructure in the marina,” Phillips said.

Two shoals exist inside the breakwaters to provide structure and ensure sediment doesn’t get into the waterway.

The last time the breakwaters were rehabilitated was in 1996, Phillips said.

Putney said one advantage with full replacement as the preferred alternative is more predictability with project bids because contractors won’t have to anticipate damaging parts of the structure that were meant to remain.

The south breakwater protects Point Hudson and the marina from crashing waves. Combined with a similar structure just to the north, it is the opening where vessels enter and exit the Point Hudson marina. (Brian McLean/Peninsula Daily News)

The south breakwater protects Point Hudson and the marina from crashing waves. Combined with a similar structure just to the north, it is the opening where vessels enter and exit the Point Hudson marina. (Brian McLean/Peninsula Daily News)

Community feedback on previous versions of a replacement plan raised concern about noise and vibrations from pile drivers and hammers, interim Executive Director Jim Pivarnik said.

“As we move forward, there was concern that all of downtown [Port Townsend] would be shaking for a period of months,” he said. “We just want to be sure we address that with the community and the contractor.”

Phillips said the soil conditions “aren’t horrible” from the perspective of using a vibratory hammer.

“This isn’t a huge pile hammer that’s going to be needed,” Phillips said. “There is some noise, but not as big or as noisy as they can be.”

Toews said there are a limited number of hammer blows allowed in a permit.

“Vibratory installation of piles really speeds up the process overall because you can get far more piles in with only proofing blows counted toward that hammer-blow count,” he said.

________

Jefferson County Managing Editor Brian McLean can be reached at 360-385-2335, ext. 6, or at bmclean@peninsuladailynews.com.

The north breakwater at Point Hudson is seen through a hole in the south breakwater, which an engineering firm suggested should be completely replaced at a cost between $5.5 million and $6.5 million. (Brian McLean/Peninsula Daily News)

The north breakwater at Point Hudson is seen through a hole in the south breakwater, which an engineering firm suggested should be completely replaced at a cost between $5.5 million and $6.5 million. (Brian McLean/Peninsula Daily News)

More in News

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas and Sue Authur, and Main Street employees, Sasha Landes, on the ladder, and marketing director Eryn Smith, spend a rainy morning decorating the community Christmas tree at the Haller Fountain on Wednesday. The tree will be lit at 4 p.m. Saturday following Santa’s arrival by the Kiwanis choo choo train. (Steve Mullensky/for Peninsula Daily News)
Decoration preparation

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas… Continue reading

Port Angeles approves balanced $200M budget

City investing in savings for capital projects

Olympic Medical Center Board President Ann Henninger, left, recognizes commissioner Jean Hordyk on Wednesday as she steps down after 30 years on the board. Hordyk, who was first elected in 1995, was honored during the meeting. (Paula Hunt/Peninsula Daily News)
OMC Commissioners to start recording meetings

Video, audio to be available online

Jefferson PUD plans to keep Sims Way project overhead

Cost significantly reduced in joint effort with port, city

Committee members sought for ‘For’ and ‘Against’ statements

The Clallam County commissioners are seeking county residents to… Continue reading

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on Saturday at the Airport Garden Center in Port Angeles. All proceeds from the event were donated to the Peninsula Friends of Animals. (Dave Logan/for Peninsula Daily News)
Santa Paws

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on… Continue reading

Peninsula lawmakers await budget

Gov. Ferguson to release supplemental plan this month

Clallam County looks to pass deficit budget

Agency sees about 7 percent rise over 2025 in expenditures

Officer testifies bullet lodged in car’s pillar

Witness says she heard gunfire at Port Angeles park

A copper rockfish caught as part of a state Department of Fish and Wildlife study in 2017. The distended eyes resulted from a pressure change as the fish was pulled up from a depth of 250 feet. (David B. Williams)
Author to highlight history of Puget Sound

Talk at PT Library to cover naming, battles, tribes

Vern Frykholm, who has made more than 500 appearances as George Washington since 2012, visits with Dave Spencer. Frykholm and 10 members of the New Dungeness Chapter, NSDAR, visited with about 30 veterans on Nov. 8, just ahead of Veterans Day. (New Dungeness Chapter DAR)
New Dungeness DAR visits veterans at senior facilities

Members of the New Dungeness Chapter, National Society Daughters of… Continue reading

Festival of Trees contest.
Contest: Vote for your favorite tree online

Olympic Medical Center Foundation’s Festival of Trees event goes through Dec. 25