The new 750-foot trestle connecting the Dungeness River Bridge to the western bank of the river is nearly completed and will be open to the public starting Thursday. Chris McDaniel/Peninsula Daily News

The new 750-foot trestle connecting the Dungeness River Bridge to the western bank of the river is nearly completed and will be open to the public starting Thursday. Chris McDaniel/Peninsula Daily News

Dungeness River Bridge set to reopen to public access Thursday; ceremony set for Dec. 30

SEQUIM — About 10 months after being damaged and closed by flooding, the Dungeness River Bridge is set to reopen to the public Thursday, Dec. 24.

The Jamestown S’Klallam tribe owns the structure and adjacent Railroad Bridge Park at 2151 W. Hendrickson Road.

A grand opening ceremony to commemorate the near completion of the $1.53 million construction project is tentatively scheduled for 1 p.m. Wednesday, Dec. 30.

“We are really pleased to be able to see it open in time for the holidays,” Annette Nesse, Jamestown S’Klallam chief operations officer, said Thursday.

Visitors now have a “sound, secure structure that should last for many, many years,” she said.

The tribe had initially scheduled the bridge to reopen earlier this month, but as “construction progressed, it looked like late December or early January,” Nesse said.

“I have to tip my hat and give a lot of kudos to Randy Johnson, our project manager, and also Nordland Construction, who have just done an amazing job of keeping that project moving forward and keeping in mind that the public is more than ready to have their structure back.”

Nordland Construction, headquartered in Port Townsend, was contracted by the tribe to complete the project using design and engineering schematics by Otak of Portland, Ore.

The new 750-foot-trestle replaces a 570-foot-long wooden trestle severely damaged by a storm in February. The damaged trestle has been demolished and removed.

The Howe Truss bridge was undamaged, but foot and bike traffic over the river has been closed since February because the old trestle connecting it to the west bank was unsafe.

That blocked a portion of the Olympic Discovery Trail, which is planned to eventually span the North Olympic Peninsula from Port Townsend to La Push.

The replacement trestle allows logs and migrating salmon to pass beneath without hindrance by reducing the number of support beams needed to prop up the walkway, the tribe said.

“The structure does not impede the river and is an important plus for salmon habitat,” Nesse said.

Finishing touches

Construction crews are putting the finishing touches on the new trestle, and some work will continue into January, Nesse said.

“They are working on the center of the crossing, which is the observation area,” she said.

“That won’t quite be complete by Dec. 24, but the main crossing over the river will be.”

The construction crew is currently awaiting the arrival of steel handrails “that were a little bit difficult to procure,” Nesse said.

“We have some temporary railings that will be up” in time for next Thursday’s opening, “and it will still be very safe for people to use the structure until” the new permanent railing is installed, she said.

The final installation date was unknown Thursday, she said.

“I know the [railings] have been ordered; it is just a matter of when it can be delivered,” she said.

The tribe also has received an additional $100,000 grant to replace the wooden decking on the existing Howe Truss bridge to match the decking on the new trestle, Nesse said.

“First Federal generously granted us some funding under their community foundation grant to redeck the bridge as well,” she said.

“That won’t be ready by the 24th. It will happen after the new year, but at some point, it will all look the same and have the same concrete decking.”

Construction phases

In early August, a demolition crew removed about 90 feet of the old wooden trestle in preparation for the construction of its replacement and to allow spawning salmon to travel through the area unhindered.

In late August, Nordland Construction began removing the remaining portions of the trestle, taking special measures to do the work without disturbing salmon and other wildlife, Thomas Johnson, president of Nordland Construction, said at the time.

The crews installed an 800-foot access road parallel to the trestle to accommodate large machinery, Johnson said.

Railroad car bridge

The temporary roadway included an 89-foot-long railroad car bridge that spanned the river channel, allowing machinery to move across and onto an island in the center without entering the waterway.

That roadway was in the process of being dismantled and removed this week, Nesse said.

Once the old trestle was completely removed in October, crews began driving steel pilings to support the new trestle into the ground at four locations.

After the steel pilings were driven, concrete piers were placed on top of the pilings to hold up the trestle.

A concrete pier beneath the existing Howe Truss bridge supports the new trestle where the two structures connect.

The new trestle began arriving in October in prefabricated 60-foot-long, 9-foot-deep sections.

The steel sections were manufactured by Wheeler Lumber LLC — a Minnesota firm that specializes in metal, fiberglass and timber prefabricated bridges — and transported to Sequim on flatbed trucks.

Crews bolted the sections together to create four 182-foot-long sections. A fifth 22-foot-long section was placed in the middle.

The final phase was to lower the walkway onto the piers with two massive cranes and install decking.

________

Sequim-Dungeness Valley Editor Chris McDaniel can be reached at 360-681-2390, ext. 5052, or cmcdaniel@peninsuladailynews.com.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading