PORT ANGELES — Design costs for the Dungeness off-channel reservoir project have exceeded estimates, forcing Clallam County to split the work into phases, commissioners heard Monday.

The long-planned, $32 million reservoir off River Road southwest of Sequim will provide 1,600 acre-feet of storage capacity to hold Dungeness River water until the late summer and early fall when irrigators and fish need it the most.

County staff members have been negotiating with Anchor QEA, a national firm with offices in Seattle and Tacoma, since April on schedule, cost and scope of work for structural and civil engineering services.

“The cost for a full, detailed design is proving to be far more expensive than we had anticipated,” county hydrogeologist Carol Creasey told commissioners Monday.

“I got sticker shock because it was almost double.”

Creasey said the proposed full design was about $1.2 million more than the $1.5 million to $1.7 million she had originally projected in 2016.

“To try and reduce that funding gap, we’re phasing the project, and I have money for Phase 1,” Creasey said.

Phase 1 will be a 30 percent preliminary design. It will cost about $900,000, Creasey said.

Commissioners on July 13 will consider approving funds for Phase 1. Those costs will largely be reimbursed by a 2019 state Department of Ecology streamflow restoration grant, according to a staff memo.

Creasey said the goal is to complete Phase 1 by the end of November to qualify for federal grants to help pay for construction of the reservoir.

“It’s pretty important to get 30 percent design done,” Creasey said.

“With that process, we have a much better shot at actually getting funding for construction.”

No commissioner objected Monday to Creasey’s request to break up the design into phases.

“I appreciate your honesty,” Commissioner Bill Peach told Creasey.

“I know what it’s like to manage a project and have it surprise.”

Creasey said her original estimate was based on the best information at the time.

Anchor QEA’s proposed bid included a project analysis, design, permitting and preparation of plans, specif¡cations and cost estimates.

Anchor QEA has experience working with Clallam County, Clallam Conservation District and the Dungeness Water Users Association, Creasey said.

The proposed off-channel reservoir would have an infiltration area for overland flow and irrigation infrastructure upgrades on state Department of Natural Resources parcels off River Road, according to a staff memo.

The 88-acre reservoir would sit atop a 320-acre parcel that will become a Clallam County park.

Water would be diverted from the Dungeness River via Highland Irrigation District’s point of diversion and conveyed through the irrigation district’s canals.

“Water would be diverted and stored in the reservoir during the winter, spring, and early summer, when flows in the Dungeness River are high and water is available,” the memo said.

“Stored water would be released to meet irrigation needs.”

County officials will discuss the project in a public meeting after Phase 1 is complete, Creasey said.

“We can expect a fair amount of engagement with the public this fall with a certain level of specificity that we just haven’t had yet, which I think will make the conversations with the public a lot more meaningful,” said Commissioner Mark Ozias, who represents the Sequim area.

In addition to her negotiations for the design, Creasey has been conducting individual outreach with farmers and irrigators, Ozias said.

The reservoir was first envisioned more than 12 years ago by a working group that included Clallam County, the city of Sequim, Jamestown S’Klallam Tribe, Dungeness Water Users Association, Clallam Conservation District, Ecology and the Washington Water Trust.

________

Reporter Rob Ollikainen can be reached at rollikainen@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading