Dredging begins at Port of Port Angeles Terminal 3

$1.6 million project to clear way for ships

PORT ANGELES — A $1.6 million dredging project began Wednesday at the Port of Port Angeles’ Terminal 3 primary cargo dock.

Port Director of Engineering Chris Hartman said the six-week underwater excavation, delayed for two months, will make it easier for captains to sidle their ships up to the pier, which, with dolphins, stretches 445 feet.

Hartman said work will include a crane operator lowering cables to the sea floor while guiding a 7-cubic-yard clamshell bucket large enough to fill two-thirds of a standard dump truck.

Two cranes will be used for the project.

The sediment will be deposited on a barge, where it will be dewatered with the aid of wall scuppers, before it’s ladled again onto dump trucks.

Drivers will deposit the silt on port property on the east end of the former KPly plywood mill site on Marine Drive just west of downtown Port Angeles.

Up to 15,000 yards of material will be dropped on about 4 acres of the mostly vacant 18-acre parcel.

An interior orange fence recently was installed to prevent silt-laden runoff from migrating off the property, which will be sectioned off for analyzing the sediment.

“We have a bunch of different areas where we will do stockpiling and analytic testing to ensure it’s clean,” Hartman said.

Silt that meets state Department of Ecology pollution standards will remain and be used as fill material at the site, formerly called the Marine Trades Industrial Park.

To attract tenants, port commissioners recently renamed it the Port Angeles Marine Trades Center.

Material that exceeds Ecology standards will be trucked to the Roosevelt Regional Landfill at the Washington-Oregon border south of Yakima.

The sediment contains varying levels of polychlorinated biphenyls, pesticides, dioxins, metals, tributyltin, aromatic hydrocarbons and dioxins/furans that exceed the standards of the Dredged Material Management Program, administered by state and federal agencies.

Those levels make some of that sediment unsuitable for open-water disposal, according to the port’s Seattle-based environmental consulting firm, Floyd-Snider.

The contract includes the expectation that 3,000 cubic yards, or 5,000 tons, will need to be trucked to Roosevelt.

“We’re hoping to use as much as possible on the site so we don’t have costs for trucking and disposal,” Hartman said.

The dock area will be dug to 45 feet below mean low tide. In some places, up to 7 feet of sediment will be dug up to that depth, allowing vessels to more easily maneuver before unloading, including log ships of up to about 620 feet bound for China.

The port’s description of its pier facilities lists the dockside depth at 36.5 feet.

The area was last dredged to 45 feet in 1978.

Vessel captains have expressed concerns about hitting bottom, Hartman said in an earlier interview.

Once dredging is completed again, hopes are “we do not have to do this again for another 40 years,” Hartman said Wednesday.

The project, originally scheduled for July 20-Sept. 4, was rescheduled to August, but the contractor, Legacy Contracting of Stayton, Ore., encountered delays, including problems securing the barge, Hartman said.

“The timing is not super critical other than it will be more difficult on the contractor as the weather starts to turn to rain,” he said.

“That will cause a lot more cleanup for the contractor.”

Hartman said the delay will not increase the cost to the port.

“The port is protected from that,” he said.

“We were not the cause of the delays.”

Design, sediment-core testing and permitting costs of $300,000 were not included in the contract.

Other costs that were higher than anticipated include an underestimated quantity of sediment to be removed, which increased from 13,000 cubic yards to 15,000 cubic yards, and additional soil testing that had to be conducted.

Costs over $1 million will be drawn from port reserves.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 55650, or at pgottlieb@peninsuladailynews.com.

More in News

No-contact advisory issued for Port Angeles Harbor

Clallam County Health and Human Services has issued a… Continue reading

Pamela and Ernie Burnett, left, talk about their craft items, Amijurmi — Japanese small crocheted stuffed yarn creatures — to Tracey Harris of Marrowstone Island on Saturday during the first of two days at the 38th annual Chimacum Arts and Crafts Show at Chimacum High School. (Steve Mullensky/for Peninsula Daily News)
Craft show

Pamela and Ernie Burnett, left, talk about their craft items, Amijurmi —… Continue reading

Clallam County expected to surplus 13 properties of various acreage

Historic preservation grant submitted for Port Crescent Cemetery

Recreation center spared from Jefferson County budget cuts

Officials met with city leaders to discuss continued operations

Tami McIntyre-Ceriello.
Clallam Mosaic hires new executive director

Organization provides day programming for people of all abilities

Members sought for ‘against’ committees

The Jefferson County Auditor’s Office is seeking “Against” committee… Continue reading

Hood Canal Bridge reopens after high-wind closure

The Hood Canal Bridge has reopened to traffic on Monday… Continue reading

TSR 
Steve Mullensky/for Peninsula Daily News
Chef Arron Stark gently inserts a piece of king salmon into a hot saute pan so as not to cause a splatter of hot oil. Stark was presenting a cooking demonstration to 35 people on Wednesday December 10th at the Jefferson County Fairgrounds who paid $30.00 each for the privilege of learning from one of the best chefs in the county.
Delicious demonstration

Chef Arron Stark gently inserts a piece of king salmon into a… Continue reading

Mahlum, an architecture firm, has been hired by the Sequim School District for design services related to renovation of Sequim High School and building a new Career and Technical Education building, the Ramponi Center for Technical Excellence. The high school’s renovation is part of a voter-approved bond while the CTE building is funded with grants and private contributions. (Sequim School District)
Sequim schools approve contracts

Projects approved by Public Review Committee

Andra Smith, Sequim Food Bank’s executive director, will take a job in February with the Washington Food Coalition, helping more than 300 hunger-relief agencies across the state with networking, finding new resources and understanding legislation. (Silas Crews)
Executive director to leave Sequim Food Bank

Smith accepts statewide position for hunger-relief agencies

Weekly flight operations scheduled

There will be field carrier landing practice operations for aircraft… Continue reading

Ned Hammar, left, is sworn in as Port Angeles School District Position 2 director by Clallam County Superior Court Judge Simon Barnhart on Thursday as Superintendent Michelle Olsen looks on. (Paula Hunt/Peninsula Daily News)
Hammar, Hamilton sworn in to PASD board of directors

Major foundation work complete on Hurricane Ridge Middle School