Downtown Port Angeles projects continuing

PORT ANGELES — Another concrete pour for the Port Angeles International Gateway Transportation Center is scheduled for today, but it won’t require street closures as last week’s project did.

The concrete is for the walls of the project’s western garage.

Work up to now has consisted of building the forms and rebar for the garage’s walls.

Last Monday, about 700 cubic yards of concrete was poured for the project’s pavilion deck to the east, requiring temporary closure of a portion of Lincoln Street.

The $13.8 million Gateway Center will include a transit building with a public plaza topped by a pavilion roof, clock tower, a bus lane and a two-tier parking garage.

It is being built along Lincoln Street between Railroad Avenue and Front Street.

Primo Construction of Carlsborg began construction last June and is expected to finish in late summer.

Installation of the large stormwater filter unit underneath the MV Coho ferry terminal was completed prior to today’s resumption of ferry service following a two-week maintenance period.

But stormwater drainage lines continue to be installed along Railroad Avenue.

The street will remain open with traffic being reduced, as necessary, to one lane and controlled by flaggers to provide two-way access.

Although some work in the area will continue this week, Coho passengers will have full access to the terminal.

The planned five-day closure of Laurel Street between the alley and Railroad Avenue has been delayed until the storm water line work along Railroad Avenue is completed.

The work will involve installing storm water drainage lines down the middle of Laurel Street.

Farther to the north and west, work continues on the $2.4 million downtown sidewalk and water main project being built by IMCO General Construction of Bellingham.

Water mains have been installed along Front Street between Laurel and Oak streets and customers have been switched over.

Front Street between Laurel and Oak streets will return to two lanes this week, but the north lane still will close periodically to complete construction of the sidewalk walls, and installation of the curbs and pavers.

Work also continues on the south side of First Street between Cherry and Oak streets.

Parking on the south side of the street will be prohibited with periodic closures of the south traffic lane as necessary.

Closure of Laurel Street between Front and First streets will continue during reconstruction of the sidewalk on the street’s west side.

The failing sidewalk was removed and footings, columns and beams are being installed to support the new sidewalk over the historical Port Angeles Underground area below.

Businesses remain open with pedestrian access across temporary footbridges.

Construction work is scheduled between 7:30 a.m. and 4:30 p.m., Monday through Friday, after which traffic lanes on Laurel, First and Front street will reopen to traffic.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading