DOT ‘didn’t anticipate’ size of Tuesday backup

Port Angeles traffic halted for hours

PORT ANGELES – A failure of imagination and a lack of communication led to a daylong traffic jam in downtown Port Angeles on Tuesday.

“We didn’t anticipate a backup of that size. We apologize profusely to everyone involved and we are working to ensure that never happens again,” said April Leigh, state Department of Transportation spokeswoman, on Wednesday afternoon.

The maintenance crew closed the right lane of eastbound First Street at milepost 248.9 (Chambers Street) shortly before 6 a.m. to conduct a “dig out and patch” pavement repair, Leigh said.

A traffic alert on DOT’s app and website stated the work would end about 4 p.m. but the crew worked until about 5:45 p.m. to finish. The alert characterized the traffic flow as “stop-and-go.”

People took to social media virtually all day Tuesday to share their horror stories about being caught in the traffic mess. They described taking an hour to get from Peabody to Chambers streets, being unable to get down from Peninsula College, taking two hours to get from the Marine Drive Chevron up to Swain’s General Store, taking an hour and 45 minutes to get from Peabody Street to Deer Park Road and traffic backing up Race Street all the way to Eighth Street.

Clallam 2 Fire-Rescue Chief Jake Patterson said at about 5:30 p.m. that traffic still was backed up in the 1000, 1100 and 1200 blocks of First Street including in front of the fire district’s office at 1212 E. First St.

Leigh said DOT officials don’t anticipate any other work like Tuesday’s. Some repairs on U.S. Highway 101 between Port Angeles and Sequim are planned but those will come with advance notice, she said.

In answer to the question on everyone’s mind, Leigh said the work was done during the day instead of at night in the interest of worker safety.

“I know our maintenance teams are doing more day work for safety reasons. We’ve had increased accidents in our work zones,” Leigh said.

“In general, we are doing more day work because it is safer. The work zones are more visible than at night,” she said.

Mike Healy, Port Angeles Public Works director, said Wednesday that, usually, the city and DOT communicate very well about road projects.

“But (Tuesday) something went awry,” he said. “We had no advance notice.

“For the safety of their worksite and our residents and travelers we could have come up with a solution for what turned out to be a pretty good mess,” he said.

Leigh said she didn’t know why no advance notice was given.

Healy said if the city had advance notice, the public works department could have attempted to mitigate it with altering the signal timing to improve traffic flow and prohibiting on-street parking so the parking lane or bike lane could be used for traffic.

The department had its traffic engineers out early Wednesday morning to see what and where and when they could make some adjustments, Healy said.

“As soon as we get some information from them, we will get something out to the public. We apologize to the traveling public and our residents but we were caught totally off guard,” he said.

“(DOT) are good people. We have been reaching out to them since 6:30-7. Hopefully we can re-establish that communication link and see how we can help them. Our communication on those projects has been very good to date,” Healy said.

Jim Fetzer, Clallam Transit System operations manager, wrote in a Wednesday morning email that the transit agency was notified through the communication channels used for the public.

“We have signed up and receive email alerts regarding WSDOT construction, road projects, Hood Canal updates and so on.

“It appears we received an alert on June 6th at 1:43pm. I am not aware of any alerts other than (that email.”

Fetzer wrote that the most heavily impacted routes were the 30 – Commuter, 20 – College Route, and 50 – Jamestown.

“These routes were running 30-plus minutes behind. The construction did cause difficulties with buses leaving Gateway and because of the traffic delays, some bus trips were missed. It is difficult when one lane is closed on 101, especially during business hours,” Fetzer said.

“Detour options in this area are very limited, and the traffic backs up quickly.

“Even when we receive advance notice on these types of lane closures which occur during peak business hours, there isn’t much we can do, and we end up experiencing significant delays.”

________

Reporter Brian Gawley can be reached at 360-452-2345, ext. 55650, or at brian.gawley@soundpublishing.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading