Cross-Strait power line won’t be ready until 2008

PORT ANGELES — A planned high-voltage power line under the Strait of Juan de Fuca to Victoria won’t be operational until the end of 2008, a year later than projected, the project’s manager told the Planning Commission at its Wednesday night meeting.

The Planning Commission recommended state Department of Ecology approval of the project’s shoreline substantial development conditional use permit.

The 550-megawatt transmission line — one megawatt is enough to power about 625 homes — would extend from View Royal on the Portage Inlet near Victoria to the Bonneville Power Administration’s substation at Park Avenue and Porter Streets in Port Angeles, just west of the Peninsula College campus.

The cable would use “high voltage direct current light,” a variation of “high voltage direct current” that is being used in cables already in the Strait of Juan de Fuca.

A converter station would be built just south of Lauridsen Boulevard, north of the Bonneville Power Administration substation.

The cable would be about eight inches thick on land and 10 inches under water.

Mike Wise, project manager for Sea Breeze Victoria Converter Corp., said the plan was expected to be operational at the end of 2007 but now the target date has been pushed to the end of 2008.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

The aurora borealis shines over Port Townsend late Monday night. Ideal conditions to view the event are from about 9 p.m. to 3 a.m. with clear skies and away from city lights or higher locations with northern views. (Steve Mullensky/for Peninsula Daily News)
Northern lights

The aurora borealis shines over Port Townsend late Monday night. Ideal conditions… Continue reading

Jefferson County board sets annual goals

Discussions include housing, pool, artificial intelligence

Clallam commissioners to continue policy discussions on RVs, ADUs

Board decides to hold future workshop before finalizing ordinance

Port Angeles School District community conversation set Thursday

Individuals who want to talk to Port Angeles School… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading