Cross-Strait cable almost ready to go

A proposed 550-megawatt transmission line that connect the power grids on the Olympic Peninsula and Vancouver Island has received the approval of the U.S. Army Corps of Engineers — which removed the last hurdle for construction on the American side of the Strait.

The Sea Breeze Pacific Juan de Fuca Cable LP’s line would leave Vancouver Island from Esquimalt, near Victoria, and connect with Port Angeles near the former Rayonier Inc. pulp mill site, located at the end of North Ennis Street on the city’s waterfront.

Construction of the estimated $350 million project is expected to begin in mid- to late-2009, said Sara Mitchell, project coordinator with the Vancouver, British Columbia-based Sea Breeze Power Corp., which conceived of the cable in 2004.

Construction could take up to 18 months, she said.

The Army Corps of Engineers permit authorizes the cable to be constructed on U.S. soil and seabed.

In September, Sea Breeze also received a permit from the state Department of Ecology, which laid out the water quality and pollution requirements of the project.

The U.S. Department of Energy issued Sea Breeze a Presidential Permit, which addresses impacts on the environment and U.S. electric transmission system, on June 12.

Sea Breeze claims that both the Corps of Engineers permit and the Canadian National Energy Board permit issued in September 2006 are firsts for a private-sector led international transmission project.

Energy from the island

The cable would allow Sea Breeze to sell energy, particularly renewable energy, into the United States from Vancouver Island.

Sea Breeze Power Corp. has a 450-megawatt wind farm permitted on Vancouver Island and a 25-megawatt run-of-river hydro project in the permitting process on the Canadian mainland, said the company’s Web site, www.jdfcable.com.

The cross-border transmission line along the I-5 corridor is considered congested, Mitchell said.

“The big factor is renewable energy demand in the [United States],” she said.

Another $150 million in electrical system upgrades are expected to be needed to handle the additional capacity that would come from Vancouver Island.

How that cost may be distributed has yet to be determined, Mitchell said.

Mitchell said Sea Breeze still needs:

âñ  An aquatic land lease agreement with the state Department of Natural Resources.

âñ  A renewed noise variance for construction from the city of Port Angeles.

The variance was approved in 2006, but has since expired.

It allowed Sea Breeze to conduct 23 consecutive days and nights of tunnel boring on Liberty Street between Caroline and Georgiana streets, about three blocks east and one block south of Olympic Medical Center.

âñ  Storm water and building permits.

âñ  An environmental assessment from three Canadian federal agencies.

Ecology & Environment Inc. from Seattle is consulting with Sea Breeze on all of its U.S. permits.

Mitchell said the company is still seeking a lease agreement with Clallam County Public Utility District for the construction of a converter station adjacent to the Peninsula College campus in Port Angeles.

Construction of the cable was initially expected for early 2007.

Mitchell said Sea Breeze didn’t expect the permitting process to take this long, particularly on the Canadian side.

A private-led submarine trans-border cable project is unique to Canadian and U.S. federal agencies, which is why the permitting has taken longer than expected, she added.

“There is not a precedent for this,” she said.

A ship-towed machine would dig a trench between three feet and six feet deep to lay the cable under the Strait and cover the trench.

On land, the cable would be about eight inches thick. It would be 10 inches in diameter under water.

Mitchell said a horizontal directional drilling machine would be used to drill 700 to 800 meters under the harbor’s shoreline and other environmentally-sensitive areas to connect with the cable.

The machine would likely need to operate on the Rayonier site, she added.

________

Reporter Tom Callis can be reached at 360-417-3532 or tom.callis@peninsuladailynews.com.

More in News

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas and Sue Authur, and Main Street employees, Sasha Landes, on the ladder, and marketing director Eryn Smith, spend a rainy morning decorating the community Christmas tree at the Haller Fountain on Wednesday. The tree will be lit at 4 p.m. Saturday following Santa’s arrival by the Kiwanis choo choo train. (Steve Mullensky/for Peninsula Daily News)
Decoration preparation

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas… Continue reading

Port Angeles approves balanced $200M budget

City investing in savings for capital projects

Olympic Medical Center Board President Ann Henninger, left, recognizes commissioner Jean Hordyk on Wednesday as she steps down after 30 years on the board. Hordyk, who was first elected in 1995, was honored during the meeting. (Paula Hunt/Peninsula Daily News)
OMC Commissioners to start recording meetings

Video, audio to be available online

Jefferson PUD plans to keep Sims Way project overhead

Cost significantly reduced in joint effort with port, city

Committee members sought for ‘For’ and ‘Against’ statements

The Clallam County commissioners are seeking county residents to… Continue reading

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on Saturday at the Airport Garden Center in Port Angeles. All proceeds from the event were donated to the Peninsula Friends of Animals. (Dave Logan/for Peninsula Daily News)
Santa Paws

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on… Continue reading

Peninsula lawmakers await budget

Gov. Ferguson to release supplemental plan this month

Clallam County looks to pass deficit budget

Agency sees about 7 percent rise over 2025 in expenditures

Officer testifies bullet lodged in car’s pillar

Witness says she heard gunfire at Port Angeles park

A copper rockfish caught as part of a state Department of Fish and Wildlife study in 2017. The distended eyes resulted from a pressure change as the fish was pulled up from a depth of 250 feet. (David B. Williams)
Author to highlight history of Puget Sound

Talk at PT Library to cover naming, battles, tribes

Vern Frykholm, who has made more than 500 appearances as George Washington since 2012, visits with Dave Spencer. Frykholm and 10 members of the New Dungeness Chapter, NSDAR, visited with about 30 veterans on Nov. 8, just ahead of Veterans Day. (New Dungeness Chapter DAR)
New Dungeness DAR visits veterans at senior facilities

Members of the New Dungeness Chapter, National Society Daughters of… Continue reading

Festival of Trees contest.
Contest: Vote for your favorite tree online

Olympic Medical Center Foundation’s Festival of Trees event goes through Dec. 25