Cross-Strait cable almost ready to go

A proposed 550-megawatt transmission line that connect the power grids on the Olympic Peninsula and Vancouver Island has received the approval of the U.S. Army Corps of Engineers — which removed the last hurdle for construction on the American side of the Strait.

The Sea Breeze Pacific Juan de Fuca Cable LP’s line would leave Vancouver Island from Esquimalt, near Victoria, and connect with Port Angeles near the former Rayonier Inc. pulp mill site, located at the end of North Ennis Street on the city’s waterfront.

Construction of the estimated $350 million project is expected to begin in mid- to late-2009, said Sara Mitchell, project coordinator with the Vancouver, British Columbia-based Sea Breeze Power Corp., which conceived of the cable in 2004.

Construction could take up to 18 months, she said.

The Army Corps of Engineers permit authorizes the cable to be constructed on U.S. soil and seabed.

In September, Sea Breeze also received a permit from the state Department of Ecology, which laid out the water quality and pollution requirements of the project.

The U.S. Department of Energy issued Sea Breeze a Presidential Permit, which addresses impacts on the environment and U.S. electric transmission system, on June 12.

Sea Breeze claims that both the Corps of Engineers permit and the Canadian National Energy Board permit issued in September 2006 are firsts for a private-sector led international transmission project.

Energy from the island

The cable would allow Sea Breeze to sell energy, particularly renewable energy, into the United States from Vancouver Island.

Sea Breeze Power Corp. has a 450-megawatt wind farm permitted on Vancouver Island and a 25-megawatt run-of-river hydro project in the permitting process on the Canadian mainland, said the company’s Web site, www.jdfcable.com.

The cross-border transmission line along the I-5 corridor is considered congested, Mitchell said.

“The big factor is renewable energy demand in the [United States],” she said.

Another $150 million in electrical system upgrades are expected to be needed to handle the additional capacity that would come from Vancouver Island.

How that cost may be distributed has yet to be determined, Mitchell said.

Mitchell said Sea Breeze still needs:

âñ  An aquatic land lease agreement with the state Department of Natural Resources.

âñ  A renewed noise variance for construction from the city of Port Angeles.

The variance was approved in 2006, but has since expired.

It allowed Sea Breeze to conduct 23 consecutive days and nights of tunnel boring on Liberty Street between Caroline and Georgiana streets, about three blocks east and one block south of Olympic Medical Center.

âñ  Storm water and building permits.

âñ  An environmental assessment from three Canadian federal agencies.

Ecology & Environment Inc. from Seattle is consulting with Sea Breeze on all of its U.S. permits.

Mitchell said the company is still seeking a lease agreement with Clallam County Public Utility District for the construction of a converter station adjacent to the Peninsula College campus in Port Angeles.

Construction of the cable was initially expected for early 2007.

Mitchell said Sea Breeze didn’t expect the permitting process to take this long, particularly on the Canadian side.

A private-led submarine trans-border cable project is unique to Canadian and U.S. federal agencies, which is why the permitting has taken longer than expected, she added.

“There is not a precedent for this,” she said.

A ship-towed machine would dig a trench between three feet and six feet deep to lay the cable under the Strait and cover the trench.

On land, the cable would be about eight inches thick. It would be 10 inches in diameter under water.

Mitchell said a horizontal directional drilling machine would be used to drill 700 to 800 meters under the harbor’s shoreline and other environmentally-sensitive areas to connect with the cable.

The machine would likely need to operate on the Rayonier site, she added.

________

Reporter Tom Callis can be reached at 360-417-3532 or tom.callis@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading