Crane lifts turrets into place at Dream Playground

Weekend in July possible to put on finishing touches

PORT ANGELES — Despite a flurry of last-day activity, the Generation II Dream Playground finished its planned six-day construction schedule on Sunday with much work still to be completed, but plans are already in the works for the remaining pieces to fall into place.

A scarcity of volunteer workers during the course of the week made it difficult for all tasks to be accomplished.

On Sunday afternoon — the last day of the community build — a crane arrived to lift turret roofs into place atop the frameworks of the centerpiece play structures.

Steve Methner, president of the Dream Playground Foundation, which is in charge of the build, said he was happy with the progress.

“We just had an exciting moment,” he said. “We got all of the towers set, and now it looks like a playground.

“It feels like there’s new energy here.”

Dozens of workers braved unseasonably hot temperatures on Sunday to finish as many tasks as possible before the planned stop time of 5 p.m. Methner speculated that, with the thermometer reading in the mid-90s, many older people who would have volunteered may have stayed home.

All that remained for Sunday was to finish off what detail work that could be accomplished and then button up the site.

Fencing around the playground and lesser play structures remained incomplete, but the park’s centerpiece — a “tree house” with slides and places for kids to scamper about — was finished enough to top out with the roof assemblies. A gazebo and a second play unit also received their roofs.

Methner said he and other foundation board members were leaning toward an additional weekend in July for volunteers to complete the project.

“It’s still a little bit up in the air, but we’ll have another weekend, maybe a Friday, Saturday and part of a Sunday late in July,” Methner said.

Methner said he has plans for a smaller “strike crew” of volunteers to assist with bringing the Dream Playground to its conclusion.

“We’ll also have strike crew come in to do some stuff that doesn’t need supervision or certification,” he said. “Benches, decorations and things like that so we can be as ready as we can when we do our second weekend.”

The Generation II Dream Playground replaces the original playground built by volunteers in 2002. That mostly wooden playground was razed earlier this year because of maintenance and safety issues.

Construction of the new play area was delayed from 2020 because of COVID-19.

The non-profit Dream Playground Foundation raised almost $600,000 for playground construction with dozens of contractors donating labor and equipment.

Volunteer Laurel Hargis said the new playground would be a nice gift to the children of Port Angeles and others youngsters who visit.

“I think this project is wonderful because the kids have had a tough year because of the pandemic,” she said. “What a wonderful thing to happen for them.”

Methner stepped aside for moment after the last roof piece was lowered into place and secured.

“I’m pretty emotional right now,” he said. “It’s been a year of delay and a lot of obstacles, COVID and other things, but I also feel there are a lot of amazing people who live here who step up when it’s time to step up.”

Workers secure the roof of a gazebo as it is lowered by crane on Sunday at the Generation II Dream Playground at Erickson Playfield in Port Angeles. (Keith Thorpe/Peninsula Daily News)

Workers secure the roof of a gazebo as it is lowered by crane on Sunday at the Generation II Dream Playground at Erickson Playfield in Port Angeles. (Keith Thorpe/Peninsula Daily News)

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading