Cost rises for Port of Port Angeles stormwater treatment facility construction

PORT ANGELES — The Port of Port Angeles’ Marine Terminal Stormwater Treatment facility, originally budgeted for $2.05 million, will cost $2.36 million to build and $2.73 million overall.

Port commissioners approved a construction bid Tuesday for the project north of Marine Drive on the industrial waterfront.

Commissioners Connie Beauvais, Colleen McAleer and Steve Burke unanimously approved the $2.36 million construction bid for the taxing district’s largest capital project for 2018 to low bidder Interwest Construction Inc. of Burlington.

Other project costs including $150,000 for design, $120,000 for contingency and $45,000 estimated for construction administration pushed the project cost to $2.73 million, boosting the price tag to $680,000 over budget, or 30 percent more than was allocated in the 2018 capital budget.

The $680,000 will be drawn from the port’s capital reserves, reducing the $7.5 million balance by 9 percent.

Beauvais, McAleer and Burke were unavailable for comment Tuesday afternoon.

The treatment project must be built by Sept. 30 under an administrative order from the state Department of Ecology that the port deal with untreated stormwater from the port’s industrialized shoreline are that flows freely into Port Angeles Harbor.

Construction will begin by mid- to late June, with little impact on the public expected.

A low wall and three large concrete boxes up to 5 feet tall will be installed near the port’s Terminal 3 dock off the Boat Haven parking lot.

When it went out to bid in April, the project was estimated to cost $2.05 million for construction and $200,000 for design, exceeding the budget — not including $171,000 in sales taxes — by $150,000.

Engineering Director Chris Hartman told Peninsula Daily News on April 13 that the increased cost was due to design work that made the project more “site specific,” to avoid a chemical treatment process and to expand the area planned for paving.

The cost is now $2.73 million because of the contingency amount that was added and bids came in higher than anticipated, Hartman said.

“We’ve seen construction costs escalate,” he said after the meeting Tuesday.

“That’s a portion of it, and the other part of is we budgeted the project prior to final design.

“Costs can escalate as designs get tweaked and finalized.”

Kennedy/Jenks Consultants Inc., which has an office in Seattle, was the engineering firm that did the design and construction estimate for the Marine Terminal Stormwater Treatment Project.

The project will consist of biofiltration garden and three concrete box-like cells up to 5 feet tall near the Terminal 3 dock.

It will process up to 5.5 million gallons of polluted runoff before it pours through a new outfall into the harbor.

A pump installed in the current outfall will move stormwater to the new treatment facility and will be used solely for high-rain events.

The port agreed with Ecology to install the new system after exceeding permitted levels for 12 months.

Pollutants including copper and zinc, which are toxic to salmonids, at higher levels than allowed in the permit.

Reid Middleton of Everett was the engineering firm that did the design and construction estimate for an estimated $1.63 million vessel wash-down facility that is the port’s second largest capital project for 2018.

The original construction cost estimate was $2.46 million, higher than the budgeted amount, for the facility, which will serve Westport Shipyard on Marine Drive, Platypus Marine on North Cedar and new tenants in the Marine Trades Industrial Park.

Cost reductions included transporting wash-water effluent to a nearby port treatment site instead of building a treatment facility and the option of building a 93-foot concrete wash pad that would be slightly more than half the size of a wash pad that could have more easily accommodated Westport’s 164-foot yachts.

Port officials are hoping the wash-down facility will spark tenant interest in the industrial park.

It is expected to be completed by Oct. 31. Port officials have said the wash-down is vital to development of the 18-acre site, which went through $7 million of environmental cleanup following decades as the location of a plywood mill.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 55650, or at pgottlieb@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading