Work continues Wednesday, Oct. 14, 2020, at the site of the future Field Arts & Events Hall near the Port Angeles waterfront. A fundraising slowdown driven by the COVID-19 pandemic has forced organizers to indefinitely delay construction of the center in January. (Keith Thorpe/Peninsula Daily News)

Work continues Wednesday, Oct. 14, 2020, at the site of the future Field Arts & Events Hall near the Port Angeles waterfront. A fundraising slowdown driven by the COVID-19 pandemic has forced organizers to indefinitely delay construction of the center in January. (Keith Thorpe/Peninsula Daily News)

Construction on Field Arts & Events Hall to be delayed in January

Pandemic slows fundraising efforts

PORT ANGELES — A fundraising slowdown driven by the COVID-19 pandemic has forced organizers to indefinitely delay construction of Field Arts & Events Hall beginning in January.

“The pandemic is 100 percent behind this,” Field Hall board President Brooke Taylor said Wednesday.

Taylor told the Port Angeles Chamber of Commerce during a virtual meeting earlier Wednesday that the approximately $50 million project is $10 million to $15 million short of what it needs, minus a $2 million state grant that recently gained preliminary approval.

The project is not alone in its COVID-19-related struggles, Taylor said.

“As far as what the future holds, the interesting thing is that just getting to the point where people can assemble again is not going to mean success for performing arts venues,” Taylor told meeting participants.

Taylor said in a later interview that the 41,000-square-foot glass, steel and masonry endeavor at the corner of West Front and North Laurel streets is 50 percent to 55 percent finished.

“The basic structure of the building is complete,” he said.

By January, the exterior will look like it will look when the doors open to the public, Taylor said. The landscaping will be finished by February.

Then the waiting begins.

The project — which will include a 1,000-square-foot art gallery, 500-seat performance hall, 300-seat conference area and a coffee shop — had been scheduled for completion by July.

Instead, there will be “a temporary pause in construction,” Taylor said.

He said a few variables will be at play in determining when the delay ends.

“That will be driven by, No. 1, the success of fundraising on the front end, and 2, where the pandemic restrictions take us,” Taylor said.

Before the pandemic hit last spring, organizers were ramping up to host, in a matter of months, a community capital campaign kick-off breakfast.

“We had so much planned for this summer,” Taylor said. “It’s very frustrating.”

“The hammer came down in March, and the fundraising landscape changed dramatically. It fell off a cliff.”

Taylor was planning to meet with fundraising committee members Wednesday afternoon to continue mapping out a new strategy, he said.

Social distancing guidelines make it difficult to raise funds, both face to face and at events like the breakfast that can’t be held.

Health measures also make it hard to schedule the conferences, meetings and performances that involve the kind of elbow-to-elbow contact with strangers impossible.

“The last types of activities that are going to be permitted are indoor gatherings of large groups of people,” he said.

“I can’t think of anything that would be later — the superspreaders.”

Taylor could not predict when construction might begin again.

“The one thing no one has control over is how the environment out there is going to change under COVID-19 restrictions,” he said.

“We’ve got to follow the numbers and what’s going on in the real world as far as the pandemic.

“It’s a wait and see on that end while we go full-bore on the fundraising end.”

The performing arts industry is predicting that venues may be able to reopen in 12-18 months.

But just because performance venues will reopen once a vaccine is available, it doesn’t mean patrons will return en masse.

“Regardless of the effectiveness of the vaccine, the projection is that the first year of reopening they will get 50 percent of a normal audience, then the second year, 80 percent, and have a full audience by Year 3,” Taylor said.

“For an existing venue that is bleeding money, they have to open under any circumstances to get some money in.

“It does not make sense for us to do that since we can effectively time our opening.”

The flip side of that: Conference and entertainment planners must schedule events several months in advance but cannot offer specific dates.

“Performance groups won’t commit because they have no certainty,” Taylor said.

“It’s a real can of worms when you realistically stop to think about programming and the lead time you need to do effective programming.”

Field Hall is being built by Minneapolis-based M.A. Mortenson Company with Clallam County subcontractors including Olympic Electric and Angeles Concrete of Port Angeles, and Jamestown Excavating of Sequim.

Most of their work is completed, Taylor said.

The final project cost won’t be known until the end of January, he added.

Taylor had estimated the cost of the project at $30 million to $31 million in August 2019.

“It’s been a moving target from Day 1,” Taylor said.

“I should never have projected it.”

The current estimate of about $50 million is “pretty solid right now,” he said.

“It will obviously fluctuate some, depending on market conditions.”

Taylor pointed to the $2 million grant as a vote of confidence in the project from those in the know.

Three weeks ago, the Washington State Arts Commission, in conjunction with the state Department of Commerce, recommended that state lawmakers approve the award.

Field Hall was the top-rated recipient among 18 applicants and would receive the maximum-allowable grant.

“It was a complete validation of what we are doing despite their knowledge of the temporary construction pause, and that was very rewarding,” Taylor said.

“They liked what we are doing, checking all the boxes.

“They think it’s a plus rather than a negative that we are making this prudent business decision.”

Field Hall is on a 1.6-acre parcel purchased with a $1.43 million donation from Dorothy Field.

It will include a facility run jointly by the Feiro Marine Life Center and Olympic Coast National Marine Sanctuary and a cultural center operated by the Lower Elwha Klallam Tribe. It is known collectively as the Port Angeles Waterfront Center.

Feiro Executive Director Melissa Williams and Tribal Chairwoman Frances Charles could not be reached late Wednesday afternoon for comment on the status of the other two projects planned for the site.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 55650, or at pgottlieb@peninsuladailynews.com.

Terry Ward, publisher of the Peninsula Daily News, Sequim Gazette and Forks Forum, serves on the Port Angeles Chamber of Commerce board of directors.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading