Construction of span over Elwha River stretches toward September completion

11The two-deck structure already has taken shape. Clallam County public works officials said the bridge will likely open in late September.

“It’s the biggest job in Clallam County history, so it’s a major undertaking,” said Jim Steeby, construction inspector for the county.

The project is virtually on schedule and on budget.

“We’ve spent some of our contingency monies, which is expected, but we’re still within the overall budget,” said Craig Jacobs, Clallam County public works director.

The project is being funded through state, tribal and federal dollars. The original estimate was $16.4 million.

Pedestrian path

A 14-foot-wide pedestrian path will hang below the 28-foot-wide automobile deck. The vehicle deck is already finished.

The foot and bike path will become part of the Olympic Discovery Trail.

“Some of the local bicycle groups are chomping at the bit to get out here and use this thing,” Steeby said. “It’s pretty neat.”

Pre-built, 8-foot sections of concrete and rebar will form the pedestrian deck.

Each section is suspended to the main deck by 21âÑ2 inch thick cables.

“Then they all get tied together and routed in place, so there’s quite an operation that goes on there,” said Ross Tyler, Clallam County engineer.

A pair of large brace frames will keep the bridge from swaying from side to side.

As of Friday, 43 of 56 sections were locked in place. The foot deck is being built from east to west.

Crews are hanging an average of three to five panels per day, Steeby said. The remaining panels should be done by midweek.

Minneapolis bridge collapse

State officials closed the creaky old trestle following the catastrophic collapse of the Interstate 35W span in Minneapolis in 2007.

It was the only bridge out of 3,000 in Washington earning that distinction.

Parsons RCI was awarded the contract in July 2007.

“These guys have been working 12 or 13 hours a day trying to keep ahead of schedule,” Steeby said.

“The project, as far as I can tell, has gone pretty darn smoothly for as big as it is.”

The massive concrete columns that anchor the bridge were completed in May.

From there, the main deck was constructed with the post tension box girder technique.

Using expensive machinery, crews built the deck from the concrete pilings out and joined the sections together at the middle of the 589-foot-long span, 85-feet above the Elwha River.

Pedestrians and cyclists can expect idyllic views of the Elwha River and surrounding forest after the ribbon-cutting ceremony this fall.

________

Reporter Rob Ollikainen can be reached at 360-417-3537 or at rob.ollikainen@peninsuladailynews.com

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading