Clallam County faced with $1.7 million dilemma on McDonald Creek bridge replacement

Officials must decide whether to spend money on temporary span near Agnew or reroute traffic for eight months in 2017.

PORT ANGELES — Pick your poison: an eight-month closure of Old Olympic Highway at McDonald Creek or spend $1.7 million on a temporary bridge.

That’s the dilemma facing Clallam County officials as they prepare to replace the 60-year-old McDonald Creek bridge in 2017.

Public input will help determine whether the county spends taxpayer money on a temporary span or diverts east-west traffic onto U.S. Highway 101 for up to eight months next year.

“We need a decision somewhere between now and when we break ground on this very critical thing, because it’s going to affect a lot of drivers,” County Engineer Ross Tyler told commissioners Monday.

If a temporary bridge is not installed, westbound motorists would detour 1.5 miles from Old Olympic Highway to U.S. Highway 101 along Kitchen-Dick Road.

From there, it’s 1.8 miles to North Barr Road and another 1.3 miles back to Old Olympic Highway.

The project site near McDonald Creek will be closed throughout construction except for local access to private driveways west of the bridge, according to the scope of work.

Call for bids

A call for bids for the $4.73 million project will be issued in December. The estimated cost does not include the installation of a temporary bridge.

Construction will commence early next year, Assistant County Engineer Joe Donisi said.

“We’re expecting that road to be closed for up to eight months to do this project if we don’t put a temporary bridge in,” Donisi said of Old Olympic Highway.

Two options

“So those are our two options: an eight-month closure and utilize the 101 as the way around, or try to pay $1.7 million for a temporary bridge.”

The new bridge will be 40-feet wide — the same width as the rest of Old Olympic Highway in the Agnew area — with eight-foot shoulders on each side.

It will be funded with $3 million in county real estate excise taxes, $922,000 in county road funds and $808,000 in Federal Highway Bridge Preservation Funds.

“We’re kind of short on funds on this project, and it’s a mostly county-funded project,” Donisi said in the board work session.

Clallam County received federal money to complete a seismic retrofit of the aging bridge several years ago.

Replace the bridge

County officials later decided to replace the bridge for safety reasons.

“It’s a 1956 bridge,” Donisi said. “It’s very narrow, and we’re really looking forward to having a full-width bridge there that matches the road on each side of it.”

Commissioners next Tuesday will consider a supplemental agreement with BergerABAM, Inc., to prepare the plans, specifications and estimates for the new bridge.

“This basically gets them into the full-blown design,” Tyler said.

Meanwhile, the Clallam County Road Department will disseminate information about its two options for Old Olympic Highway and schedule public meetings to gather feedback from residents.

“I don’t even want to convene a public meeting at the grange or something like that until we’ve got enough time for that [information] to settle out to the locals out there so we can get good attendance here,” Tyler told commissioners.

“We need to have everybody out there, so this won’t be the only time you hear that subject. We’re going to be real loud with it.”

Tyler added: “We’ve got to figure out — and we want everybody’s input — what’s going to be the best way to go here.”

________

Reporter Rob Ollikainen can be reached at 360-452-2345, ext. 56450, or at rollikainen@peninsuladailynews.com.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading