Clallam County commissioners consider backing Carlsborg sewer project

PORT ANGELES — A major sticking point in the long-proposed Carlsborg sewer project has been how to pay for it.

That question will be answered in part today if the Clallam County commissioners approve the use of rural economic development funds to back pay a $10 million state loan to build the a Class A sewer and wastewater treatment facility off Carlsborg Road.

The county’s “Opportunity Fund” is a short name for the Rural Counties Economic Development Act Fund, a nine-tenths of 1 percent portion of state sales tax.

“It’s something the state gave to rural counties that don’t get a lot of sales tax revenue,” County Administrator Jim Jones said.

The money can be used at commissioners’ discretion for public infrastructure projects that lead to economic development, Jones said.

$900,000 per year

Clallam County’s share of the state funding is about $900,000 per year.

The county and the Clallam County Public Utilities District are partners in the decade-old proposal to build a $15 to $17 million Class A sewer and treatment plant.

The PUD will operate the facility if the county follows through on building it.

Commissioners today will consider authorizing a $450,000-per-year repayment of the $10 million Public Works Trust Fund Loan from the Opportunity Fund.

A condition in the resolution requires that the necessary loan documents, permits and agreements with the PUD be signed before the Opportunity Fund can be tapped.

Commissioner Steve Tharinger said the Opportunity Fund will give the county “flexibility in structuring how the payment structure will be set up.”

The cost to individual property owners has not been determined.

“There’s quite a few steps still necessary to go through,” Jones said. “This resolution is just basically saying, this is the board’s wish.”

Reasons for support

Two of the major reasons that the commissioners support the sewer are:

■ Nitrate and other groundwater pollution from existing septic tanks.

The Clallam County Board of Health supports the project for this reason.

Some opponents of the sewer project say existing septic systems have not been proven to be the source of the nitrate pollution.

■ A Growth Management Act hearings board ruling in 2008 that found the Carlsborg Urban Growth Area invalid and non-compliant with state law because it lacked adequate urban infrastructure or funding for a sewer.

Businesses can’t expand under interim zoning rules that have been extended six times for sixth months at a time.

The sewer issue has pitted some residences against business owners who want to expand but can’t because a lack of a sewer.

About a year ago, the grass-roots Citizens For the Preservation of Carlsborg submitted a petition with more than 170 signatures from property owners opposed to the sewer.

Cost a big concern

Cost was cited cost as the chief concern in a series of public hearings on interim zoning.

Some sewer opponents have said they would like the UGA to be abolished altogether, and for Carlsborg to be redesignated as rural.

Carlsborg because an urban growth area in 2000.

County commissioners this month said they support the sewer because of the economic benefits.

Carlsborg supports more than 1,000 jobs.

The PUD was awarded the $10 million, 0.5 percent-interest Public Works Trust Fund loan in May.

The state loan has a five-year deferral and can be repaid over 30 years.

The project has been in Clallam County‘s capital facilities plan since 2009.

Clallam County had already committed $4 million to the project.

________

Reporter Rob Ollikainen can be reached at 360-417-3537 or at rob.ollikainen@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading