Carlsborg sewer system envisioned for completion in 2012

CARLSBORG — Carlsborg could have a wastewater treatment and reuse system up and running by the middle of 2012, according to a pre-draft sewer facilities plan.

John Wilson, an engineer with Seattle-based BHC Consultants, presented the preliminary draft to the three Clallam County commissioners and the Clallam County Public Utilities District commissioners earlier this week.

He will expand on that presentation in a public forum from 6 p.m. to 8 p.m. Thursday at Greywolf Elementary School, 171 Carlsborg Road, Sequim.

The sewer for the Carlsborg Urban Growth Area is a joint proposal of Clallam County and the Clallam County Public Utilities District No.1.

The governing bodies have signed a memorandum of understanding to jointly develop the sewer for the growing, unincorporated village west of Sequim.

Once completed, the PUD will become the owner and operator of the system.

Wilson led a Carlsborg sewer feasibility study, which was approved by the county and the PUD last year.

Nearly $15 million

The estimated cost of the sewer system is $14,970,000.

About a third of that would come from local, state and federal grants, Wilson said.

The remainder would be assessed to property owners.

According to Wilson’s estimates, the monthly fee would be $62.50 in the first few years of its operation.

As more and more residents tap into the system, the cost would fall to about $50.

The initial sewer would run a main trunk north and south along Carlsborg Road to a treatment facility with percolation basin near Runnion Road and Carlsborg Road.

The treated Class A water would filter from the percolation basin into Matriotti Creek.

Property owners who decide to tap into the system down the road will have that option, Wilson said. The initial system will have 120 hookups, according to the pre-draft plan.

The facility would be built for future expansion and to handle estimated demand for 2050.

Clallam County has a vested interest in the sewer system because Carlsborg was ruled non-compliant and invalid with the Growth Management Act by a state hearings board.

Urban services

Urban Growth Areas are required to have such urban services as sewers.

“We considered a bunch of alternatives,” Wilson told the county commissioners.

“Let’s start by saying, of course, we looked at the city of Sequim option for treatment and disposal.”

It would be about 10 percent cheaper to transmit wastewater across the Dungeness River to the Sequim sewer system. However, if the water is to be brought back to Carlsborg for reuse in the groundwater supply, it’s about 10 percent cheaper to build a new facility, Wilson said.

Treated water can be used for irrigation, riparian habitat and recharging the aquifer.

Water conservation and reuse is a high priority in a water-short Water Resource Inventory Area 18, which includes Carlsborg.

A full environmental review with state Department of Ecology approval would precede any construction.

On-site septic systems are leaking nitrates into the groundwater, according to the language in the pre-draft facilities plan.

Nitrate concentrations have risen to approach or exceed maximum levels for drinking water, and the treatment and reuse system would remove those nitrates and “get a good reduction of phosphorus,” Wilson said.

A draft time line targets October 2010 for environmental approval, January 2011 for construction start and July 2012 for customer connection.

________

Reporter Rob Ollikainen can be reached at 360-417-3537 or at rob.ollikainen@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading