Building work on schedule for new Port Townsend-Keystone ferry

SEATTLE — Work accelerated in January on the 64-car ferry Chetzemoka, which is on schedule to launch this summer to serve the Port Townsend-Keystone route.

The new ferry will launch almost three years after the 80-year-old Steel Electric ferries were pulled from the Admiralty Inlet route for safety reasons, crippling ferry service between the North Olympic Peninsula and Whidbey Island.

The route has been since served by one 50-car ferry, the Steilacoom II, which Washington State Ferries leases from Pierce County.

The narrow and often shallow constraints of Keystone Harbor on Whidbey Island prevent the use of a larger ferry on the Port Townsend-Keystone route.

Todd Pacific Shipyards, starting in June, built the Chetzemoka’s bow inside a construction building on Seattle’s Harbor island, rolling it out onto dry dock in mid-January.

A 105-ton section of the passenger deck arrived Jan. 18 via barge from Nichols Brothers Boat Builders of Freeland, on Whidbey Island, and the structure was lifted into place atop the hull.

The pilothouses also arrived from Nichols Brothers and were hoisted with giant cranes onto the hull.

Construction crews are now attaching the superstructure, installing shafting and rudders.

During the good weather, crews are painting the vessel.

The state ferries system plans to build three or four new 64-car ferries in the next several years to replace parts of its aging fleet.

Nine of the ferries division’s 20 auto-passenger ferries are between 40 and 65 years old and must be replaced in the next 20 years. The last new state ferry was put into service in 1999.

The first two 64-car ferries will be assigned to the Port Townsend-Keystone route, restoring two-boat service with state-owned ferries to that route.

The new vessels will reduce the number of weather cancellations on the Port Townsend-Keystone route and will improve service, state ferries officials said.

Work on the second 64-car ferry is expected to begin this year.

The state Department of Transportation awarded a $65.5 million contract to Todd Pacific Shipyards in December 2008 to build the first 64-car ferry.

A second $114 million contract was awarded in October to Todd for a second and third 64-car ferry.

More in News

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas and Sue Authur, and Main Street employees, Sasha Landes, on the ladder, and marketing director Eryn Smith, spend a rainy morning decorating the community Christmas tree at the Haller Fountain on Wednesday. The tree will be lit at 4 p.m. Saturday following Santa’s arrival by the Kiwanis choo choo train. (Steve Mullensky/for Peninsula Daily News)
Decoration preparation

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas… Continue reading

Port Angeles approves balanced $200M budget

City investing in savings for capital projects

Olympic Medical Center Board President Ann Henninger, left, recognizes commissioner Jean Hordyk on Wednesday as she steps down after 30 years on the board. Hordyk, who was first elected in 1995, was honored during the meeting. (Paula Hunt/Peninsula Daily News)
OMC Commissioners to start recording meetings

Video, audio to be available online

Jefferson PUD plans to keep Sims Way project overhead

Cost significantly reduced in joint effort with port, city

Committee members sought for ‘For’ and ‘Against’ statements

The Clallam County commissioners are seeking county residents to… Continue reading

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on Saturday at the Airport Garden Center in Port Angeles. All proceeds from the event were donated to the Peninsula Friends of Animals. (Dave Logan/for Peninsula Daily News)
Santa Paws

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on… Continue reading

Peninsula lawmakers await budget

Gov. Ferguson to release supplemental plan this month

Clallam County looks to pass deficit budget

Agency sees about 7 percent rise over 2025 in expenditures

Officer testifies bullet lodged in car’s pillar

Witness says she heard gunfire at Port Angeles park

A copper rockfish caught as part of a state Department of Fish and Wildlife study in 2017. The distended eyes resulted from a pressure change as the fish was pulled up from a depth of 250 feet. (David B. Williams)
Author to highlight history of Puget Sound

Talk at PT Library to cover naming, battles, tribes

Vern Frykholm, who has made more than 500 appearances as George Washington since 2012, visits with Dave Spencer. Frykholm and 10 members of the New Dungeness Chapter, NSDAR, visited with about 30 veterans on Nov. 8, just ahead of Veterans Day. (New Dungeness Chapter DAR)
New Dungeness DAR visits veterans at senior facilities

Members of the New Dungeness Chapter, National Society Daughters of… Continue reading

Festival of Trees contest.
Contest: Vote for your favorite tree online

Olympic Medical Center Foundation’s Festival of Trees event goes through Dec. 25