Big Port Angeles bridges project may take less time

PORT ANGELES – When the two Eighth Street bridges close later this summer, it could be for a shorter time period than first anticipated.

City Traffic Engineer Jim Mahlum said the project schedule from contractor Parsons RCI Inc. of Sumner, Wash., shows the Tumwater Creek bridge closing no earlier than Aug. 1, followed by the Valley Creek bridge one month later.

Both would be reopened by Oct. 1, 2008, or 14 months later, according to the project schedule, he said.

Two weeks notice will be given prior to each bridge closing.

The city’s designated detour routes are mapped out on the Eighth Street bridges section of the city’s Web site at www.cityofpa.us.

The city has planned since 2003 to replace the twin narrow bridges that have towered over Valley and Tumwater creeks for more than 70 years.

When the project first was presented to the public in 2004, the estimated closure period for the bridges was closer to 17 months.

Mahlum said the shorter time period is due to both bridges being closed at the same time.

The original plan was to keep one lane open across both bridges during construction.

The city’s police and fire departments cited better emergency response times and eliminating the cost of substations on the city’s west side if their personnel did not have to take detours.

But in discussions with contractors, city officials were told closing both bridges at the same time would save both time and money.

The city’s fire and fire departments also have dropped the idea of building substations, opting to use the Clallam County Juvenile and Family Services Department building at 1912 W. 18th St. if necessary.

When the project originally was put out to bid in December 2005, it called for 420 working days, or about 19 months.

Mahlum said the project contract calls for 350 “working days,” or about 16 months.

Since Parsons started on June 25, that means the project is scheduled to wrap up in the middle of November 2008, he said.

He personally counted the “working days” on the calendar, Mahlum said.

City Public Works Director Glenn Cutler said at a Wednesday morning meeting at City Hall that Parsons officials would update him Monday on demolition of the bridges.

The City Council selected a slant-leg design for the new bridges in March 2004, saying it wanted a signature architectural landmark for the city.

In June 2004, steel instead of concrete was chosen for the building material, but the project had to be redesigned and rebid after the low bid came in almost 50 percent above the $20 million budget.

The redesigned project will consist of concrete spans with five or six concrete piers over each of the valleys.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading