PORT TOWNSEND — Disappointed community leaders and state Rep. Lynn Kessler vowed Thursday to work with Gov. Chris Gregoire and ferries officials to seek options after a lone bid came in $40 million over budget for two Island Home-style ferries to serve the Port Townsend-Keystone route.

Seattle-based Todd Pacific Shipyard’s proposed bid is $124,450,559 for two vessels and $65,487,328 for one.

The state has budgeted $84.5 million for the two-ferry project.

A state Department of Transportation engineer’s most recent estimate is $95,943,865 for two car ferries and $49,452,894 for one.

“It’s going to be a challenge,” said Kessler, D-Hoquiam, who represents the 24th District which covers Jefferson, Clallam and part of Grays Harbor counties.

“I’m committed, obviously, and we’re going to get a boat built,” added the House majority leader.

Less gas tax revenue

Whether two boats still can be built with additional state funds is the big question.

Kessler said state gas taxes are bringing in less transportation-earmarked revenues because motorists are driving less.

That could add to the challenge of financing a second ferry.

State ferries officials and Jefferson County ferry system advisors all voiced concerns about the high bid.

“While I appreciate Todd Shipyards’ responsiveness, I am disappointed that there is only one bid,” David Moseley, assistant transportation secretary for the state Department of Transportation’s Ferries Division, said in a written statement following the bid opening at the state ferries offices.

“We will identify all viable options before making a decision.”

If a bid from the Seattle ship builder is accepted for construction of one of the two 64-car ferries, a contract could be awarded within two weeks, state ferries officials said.

Under the existing schedule, the first vessel would be launched for the Port Townsend-Keystone route in April 2010.

“Not having that ferry is not an option,” Kessler said. “That’s our highway.

“It is going to be my very top priority for the next session.”

The legislative session next year runs from Jan. 12-April 26.

Kessler, Port Townsend Mayor Michelle Sandoval and Tim Caldwell, Jefferson County Ferry Advisory Committee chairman, met in a phone conference call Thursday with other stakeholders in the Port Townsend-Keystone Ferry Partnership Group after the bid was opened.

“Of course we will leave our options open in terms of two boats,” Sandoval said.

“We need an Island Home ferry on our waters sooner than later. It will hold more people, it will hold more cars and it will be more seaworthy.

“It’s a better boat for our route in general.”

Sandoval and Caldwell agreed that the project must begin soon.

Calling the bid “the epitome of sticker shock,” Caldwell said, “Something has to happened and has to happen within the next month.”

Caldwell said it was more than a Port Townwsend-Keystone ferry issue “because the Island Home can run on other routes.

“This is a system issue, not just a Port Townsend-Keystone issue.”

Sandoval said she and Caldwell would be among those who would meet with ferry system officials, state lawmakers, even Gov. Gregoire, to discuss the options, which are not clear at this point.

Ferries officials, led by Moseley, will be reviewing the bid over the next week to determine if it meets specifications and can be accepted.

A decision is expected within the next two weeks.

In late March, state ferries went through a similar situation when it opened, then rejected, a lone bid from Todd Shipyards for $25.98 million, about $9 million over the state engineer’s $16.8 million estimate for a 50-car Steilacoom II-model ferry for the Port Townsend-Keystone route.

It is the same model of ferry now plying Admiralty Inlet waters, which is prone to run cancellations.

Most Steilacoom II runs were canceled Thursday morning because of high winds and heavy seas.

New Year’s weekend

The Steilacoom II, which is leased from Pierce County, meanwhile, will serve the Port Townsend-Keystone route through Jan. 4 of New Year’s weekend, Moseley has said.

After that, it will under go about three weeks of annual maintenance before returning to the route.

The Coast Guard on Wednesday allowed Pierce County to extend the deadline from midnight Dec. 31 to Jan. 4, to accommodate visitors during the latter days of the holiday season through New Year’s weekend.

While the Steilacoom II is out of service, Washington State Ferries will provide passenger-only service on the Port Townsend/Keystone route, details of which are still to be worked out, Moseley said.

The state is leasing the Steilacoom II from Pierce County to fill the void left Nov. 20, when state Transportation Secretary Paula Hammond pulled the more than 80-year-old Steel Electrics. The vessels, which have been sold for scrap, serving the route because of pitted, corroded and generally unsafe hulls.

The two Island Home ferries would replace the Steel Electrics on the route.

________

Port Townsend-Jefferson County Editor Jeff Chew can be reached at 360-385-2335 or at jeff.chew@peninsuladailynews.com.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading