The dock at the former Rayonier Mill east of downtown Port Angeles, shown on Saturday, is scheduled to be dismantled beginning in mid-June. (Keith Thorpe/Peninsula Daily News)

The dock at the former Rayonier Mill east of downtown Port Angeles, shown on Saturday, is scheduled to be dismantled beginning in mid-June. (Keith Thorpe/Peninsula Daily News)

Bid adieu to last of giant dock

Rayonier pier removal slated

PORT ANGELES — An imposing, abandoned vestige of the Rayonier pulp mill’s legacy will be demolished starting in mid-June.

Workers will begin to remove the concrete panels of a 1,050-foot-long dock that juts into Port Angeles Harbor east of downtown the week of June 13 and are expected to complete it in July, pier owner Rayonier A.M. announced last week. Some of the panels were removed in November. This will finish the job.

Work at the 75-acre site, which is located within the city limits, will include removal of a warehouse on the 250-foot-wide pier and a 120-foot-long, 14-foot-wide railroad trestle across Ennis Creek.

Workers operating barge-based equipment will remove the panels and place them into barges before they are transported to the site and stacked for potential future reuse, according to the company’s State Environmental Policy Act (SEPA) checklist.

Timber debris will be transported off-site for disposal or recycling, while warehouse materials, including those with asbestos, “will be properly managed and disposed of off-site,” according to the checklist.

Trestle debris will be transferred to temporary stockpiles before being trucked off-site for disposal.

The project is part of a cleanup that’s in its 21st year.

Demolition was delayed from startup this week due to contractor scheduling issues, Rayonier A.M. spokesperson Ryan Houck said Friday in an email.

About 800 dock panels will be removed, said Joe Smillie, aquatics program communications manager for the state Department of Natural Resources, which manages the public land on which the dock sits and Rayonier A.M.’s lease to use it.

More than 5,000 toxic, decay-preventing creosote pilings will remain, spiking upward for the foreseeable future, a reminder of more than a century of timber-based manufacturing on a site that before that held the Lower Elwha Klallam village of Y’innis.

The creosote pilings are under the dock and buttress a rock jetty and breakwater.

That does not include several hundred pilings, the exact number of which is unknown, used for support for the foundation and for other pilings.

Pilings won’t be removed until 2023, when polluted sediment is dealt with as part of the company’s overall cleanup of the eastern harbor, predicted Rebecca Lawson, head of the Department of Ecology’s regional toxics cleanup program, said Friday.

“The dock is so big I don’t thing they can remove it all in one construction season,” Lawson said, adding that salmon migration restrictions limit in-water work such as piling extraction to four-six months a year.

Mill site owner Rayonier A.M. Properties LLC, a branch of Rayonier A.M., which split off from Rayonier in 2014, is removing the decking as part of its lease obligation with DNR.

“Part of the condition of the lease is cleaning [the property] up, as it is in most of our leases,” Smillie said.

“When you wind down a lease, we want you to restore it as best you can.”

Rayonier shut down March 1, 1997, after operating for 68 years on a site where other mills churned out wood products and toxins as well as creating jobs since the mid-1800s.

The federal government announced Feb. 1, 2000, that Rayonier’s “moderately contaminated” site was not toxic enough to warrant Superfund status and handed cleanup oversight to Ecology.

“‘The mill buildings themselves were taken down many years ago,” Lawson said.

“This is the first visible activity in quite a long time.”

A company official was not provided for an interview about the project or overall cleanup of the site, which will cost the company an estimated $26.6 million.

Overall cleanup will include vaporizing tainted groundwater by air sparging, dredging a log pond and dredging toxic sediment under the dock.

Dock removal is also meant to stem the incursion of homeless people who have gravitated to the fenced-off private property for shelter.

They are suspected of causing a March 5, 2019 fire that took firefighters nine hours to squelch and burned about 3,000 square feet. Authorities deemed the blaze accidental.

“The project’s purpose is to improve safety by clearing deteriorated decking and preventing trespassers from accessing the dock or trestle,” Houck said in the email.

“No in-water structures will be removed. Work will be performed using a floating derrick barge and a material barge supported by an upland crane for material offload. The project is slated to continue through July.”

The 6-acre dock, long reported to be 4 acres, is being dismantled and an adjacent jetty removed as part of Rayonier A.M. closing out its lease with DNR, Lawson said

Debris will not be allowed to enter the water or wetland around Ennis Creek, according to the sSEPA checklist filled out by a Rayonier A.M. representative and submitted to the city Department of Community and Economic Development. The agency issued a determination of nonsignificance for the project May 11.

“They will probably have to do another one when they do the rest of the work,” City Community Development Manager Emma Bolin said Friday.

She said Rayonier A.M. has been issued demolition and waste permits.

Construction will occur only during daytime hours.

The SEPA checklist included a general rundown of pollution at the site and its impact on harbor resources.

“All investigations showed exceedances of state sediment management standards, exceedances in tissue samples, and water samples for multiple constituents of potential concern, both in upland investigations, investigations in Ennis Creek, and in the marine environment adjacent to the mill,” it said.

“Recreational and commercial shellfish harvest is closed due to pollution, and the consumption of rockfish and crabs is recommended to be limited due to high levels of PCBs and dioxins.”

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 55650, or at pgottlieb@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading