Battle over biomass heats up in Longview

  • By Erik Olson Longview Daily News
  • Sunday, July 3, 2011 3:20am
  • News

By Erik Olson Longview Daily News

LONGVIEW — It’s the largest biomass energy project proposed statewide, generating enough power for 2,400 homes.

Longview Fibre Paper and Packaging officials say their 54-megawatt biomass energy expansion also would reduce air pollution and the company’s carbon footprint, plus make the mill more competitive.

But the project’s leading opponent, No Biomass Burn, says it’s the proverbial wolf in sheep’s clothing — dirty power masquerading as clean energy — and part of a growing trend among aging pulp mills.

A trend the group hopes to squash, using Longview Fibre as the test case.

“Longview is ground zero in terms of environmental fights,” Duff Badgley, coordinator for Seattle-based No Biomass Burn, said at a community meeting in Longview last week.

Burning wood waste, Badgley said, emits harmful particulates and high levels of greenhouse gases into the air.

The Seattle-based group fought eight similar proposals statewide during the last two years — two were abandoned — and it’s now setting its sights on Longview Fibre, a large and longtime employer in this southwest Washington city.

The stakes are high.

For Longview Fibre, excess biomass power could generate millions of dollars in renewable power sales on the open market.

While it’s unlikely to add full-time jobs, the project could generate work for 25 to 50 contractors daily until its completion next year, company officials said.

The mill would also shut down other, less efficient wood-waste boilers, according to the company, which is not revealing the cost of the plant.

Longview Fibre is eligible for about $30 million in federal subsidies from federal stimulus money set aside for renewable energy projects.

Nationwide, other aging pulp mills, such as the 90-year-old Nippon Paper Industries USA plant in Port Angeles, want to build similar wood waste power projects.

For many mills, renewable energy is a key component to stay in business, biomass supporters say.

“The more economical we can make manufacturing in the United States, the more chance those jobs will stay here,” said Dan Whiting, spokesman for the Washington, D.C.-based National Alliance of Forest Owners.

Pulp and paper mills who want to build these plants face a 2014 deadline.

That is when a U.S. Environmental Protection Agency three-year moratorium on regulating biomass plants for greenhouse gas emissions expires.

Failure to meet that deadline could cost energy producers millions or kill the projects altogether.

Longview Fibre is already moving forward, but the company may not be out of the regulatory woods.

The state Department of Ecology approved the company’s permit application in June.

The company began pouring concrete for the foundation later that month, company spokeswoman Sarah Taydas said.

Longview Fibre barely beat a July 1 deadline to start construction, which could have sent them on a longer and costlier regulatory path.

Badgley said No Biomass Burn plans to appeal the permit this week to the state’s Pollution Control Hearings Board, then to superior court if necessary.

He said Longview Fibre should be required to conduct a more thorough study of the project’s environmental impact.

Badgley said he helped defeat a proposed $250 million, 55-megawatt biomass energy project in Shelton.

Plant developers Areva and Duke Energy said they abandoned the project earlier this year because it would cost too much to gather enough waste wood for fuel.

But Badgley said local citizens’ opposition was the key reason, and he’s trying to build grassroots support in Longview — which is off to a slow start. At a recent community forum, nearly all of the 10 attendees were Longview Fibre supporters.

Despite the poor showing, Badgley said he plans to come back this summer because the outcome is important for other projects statewide.

“There’s a huge political dynamic here. If we beat Fibre, it will send a strong message,” he said.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading