As Clallam County Courthouse renovation winds down, third change order requested

PORT ANGELES — As renovations to the historic Clallam County Courthouse wrap up later this week, public works officials are asking for a final change order to a $347,388 contract with Advanced Construction Inc.

The $13,543 change order — the third since construction began late last year — will pay for additional rubber base, roofing, wood trim, molding, bird spikes and other items.

It also returns $3,263 for masonry that was not installed.

“Most of these items, the bigger items, were unforeseen,” Joel Winborn told the three county commissioners Monday.

Winborn is county parks, fair and facilities manager.

‘Missed in drawings’

“A couple of the things were things we just missed in the drawings,” he said.

Commissioner Steve Tharinger, who is also a state legislator, took part in Monday’s county work session by speakerphone from Olympia.

The main floor of the older wing of the courthouse was painted and remodeled. Exterior work included a new staircase for the west entrance and repairs to the clock

and bell tower.

“We’re scheduled to complete this project Thursday, and that includes the final cleaning and everything,” Winborn said.

The second and third floors of the historic courthouse were remodeled in 1999. A fuel-burning boiler was replaced with an energy-efficient electric steam boiler in 2009.

If the commissioners approve the change order today, the total cost of the project will be $360,930.

Half of the project was paid for by a 50-50 matching grant from the state Department of Archaeology and Historic Preservation.

Clallam County budgeted its share through its capital projects fund.

Built in 1914, the historic courthouse made the National Register of Historic Places in 1987.

The larger east side of the courthouse and its connecting jail were built in 1979.

Mukilteo-based Advanced Construction was selected because it submitted the lowest of four bids the county received last September.

‘Fantastic job’

“They’re doing a fantastic job,” Winborn said. “It’s just time to get them out and clean it up.”

Four county departments were temporarily relocated during construction: Washington State University Extension, the law library, environmental health and the Parks, Fair and Facilities Division.

In other discussion from Monday, County Engineer Ross Tyler told commissioners that Priest Road northeast of central Sequim will be closed for up to one week sometime between

March 15 and March 31.

The closure is needed to replace an irrigation ditch crossing. A new culvert will be installed, and humps in the road will be removed.

The irrigation ditch is four-tenths of a mile north of Washington Street.

Commissioner Mike Doherty recommended that road crews post signs during the closure that show alternate routes.

Tyler said the work will likely be finished in less than seven days.

“It’s just in the best interest of the public to be prepared for the worst-case scenario,” he said.

In other news, the county has applied for a grant renewal with the state Department of Ecology for a community litter cleanup program.

The $61,673 grant, which runs through June 2013, would pay for two Clallam County chain gang supervisors and administration costs.

Jail Superintendent Ron Sukert said the county has been successful in securing the grant “because we do well with the monies that we’ve given.”

Reporter Rob Ollikainen can be reached at 360-417-3537 or at rob.ollikainen@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading