Archaeological tests find no more Beckett Point remains; work to resume

DISCOVERY BAY – Work on a nearly $3 million Jefferson County Public Utility District community septic system at Beckett Point, which stalled in late May after prehistoric Native American remains and artifacts were uncovered, has been cleared to resume after Sept. 3, state officials said on Wednesday.

“We’re letting them go forward,” said Allyson Brooks, state historic preservation officer. “We just have to amend the permit.”

Work on the $2.8 million project will resume after Labor Day, said Jim Parker, PUD manager.

Brooks said the project could resume because no more significant cultural resources were found after 91 six-foot-deep test holes were dug where septic system “grinder pumps” and other system infrastructure would installed for Beckett Point residents, who have each paid $28,000 as their share of replacing failing septic system along there shores of shellfish-rich Discovery Bay.

Recovered sediments have been screened at each location to find any cultural materials present.

Results will be recorded, but no cultural samples will be collected, archaeologists have said.

Although shell middens were found in two locations at the Beckett Point project, Brooks said, “They should be able to move the project around the cultural resources found.”

Pape and Sons was trenching for the project in late May when 58 bone and bone fragments were discovered, shutting down the project under federal laws protecting antiquities.

In mid-July, the chief archaeologist on the site, Gary Wessen, said a single partially intact human grave was found along with concentration of other disturbed bones, stone tools and shell middens.

Shell middens are the remains of ancient beach campfires.

The late prehistoric remains were between a few hundred and a few thousand years old, Wessen reported.

In recovering remains and artifacts, Wessen and another archaeologist have been joined at the site by Jamestown S’Klallam, Port Gamble S’Klallam and Skokomish tribe representatives.

Attempts to contact Kathy Duncan, cultural resources manager for the Jamestown S’Klallam tribe, were unsuccessful on Wednesday.

Wessen, with Wessen and Associates, has submitted “An Archaeological Survey and Evaluation of the Beckett Point Study Area” to PUD, the state archaeology office and the tribes, Parker said.

Parker said he hopes that contractor Pape and Sons can complete the project before winter’s high tides hit and flood the lagoon at Beckett Point.

“The contractor can start digging holes and put in grinder pumps and start connecting them,” Parker said on Wednesday.

Grinder pumps will move wastewater from individual Beckett Point homes into the already-installed sewer line. From there, wastewater will be pumped to a drain field that is uphill of the Beckett Point village, away from Discovery Bay.

The upper drain-field portion of the project was cleared earlier for continued drain-field work, and has been monitored by an archaeologist.

Archaeological work for the site study has come to $30,000 so far, with Jefferson County paying $18,000, Parker said.

Officials with the state Department of Archeology and Historic Preservation came up with a $10,000 grant for early work.

Additional costs caused by construction delays and additional engineering work have not yet been calculated, Parker said.

PUD commissioners agreed to work with the Jamestown, Port Gamble and Skokomish tribes, as well as the state archeology office to ensure that remains or artifacts will be uncovered and properly handled.

Septic system work has yet to be extended to homes along Beckett Point’s Viewpoint Lane because work stopped short of that link in the project.

Three North Olympic Peninsula lawmakers sent a letter of support to the state Department of Ecology water quality division in support of a $250,000 grant to aid the project, but the application was rejected because Ecology said it did not fit the criteria of a pilot project.

Describing the cultural setting in his report, Wessen said Beckett Point was occupied by S’Klallam and Chimera Indian Peoples during the early historic period.

Report

Wessen and Associates’ study researched the history of Beckett Point, conducted a surface survey and investigated buried deposits from the test holes and two backhoe-dug trenches, the report states.

“This work has identified four areas of potentially intact shell midden deposits and five additional areas where clearly disturbed shell midden materials are present,” the report said.

“The potentially intact shell midden deposits are yet to be investigated in detail, but the currently available information suggests that they represent relatively recent late prehistoric Native American use of this area. Both occupation areas and a cemetery appear to be represented.”

The study proposed modifying the project’s existing engineering plans to move some project infrastructure, including one grinder pump and some release valves, to avoid disturbing shell midden areas.

The possible presence of additional graves and/or disturbed human bones remains a concern throughout the study area, Wessen reported.

“While this possibility may seem relatively small in some portions of the area, we believe that it must be respected,” Wessen said, recommending that an archaeologist continue to monitor the project until it is complete.

________

Port Townsend-Jefferson County Editor Jeff Chew can be reached at 360-385-2335 or jeff.chew@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading