$20 million construction project continues on schedule, budget at Jefferson Healthcare hospital

PORT TOWNSEND — Phase three of the $20 million construction project at Jefferson Healthcare is proceeding on schedule and within budget.

When work is completed, which is currently expected to happen in late summer 2016, it will result in a new emergency and special services building, which would open later in the year.

“We are hoping it is going to be late next year,” Kate Burke, Jefferson Healthcare marketing manager, said Monday.

“Right now, that seems to be falling into line. The construction project seems to be on track.”

The project is necessary because “our outpatient services are growing rapidly, and we are trying to plan for the future as well as to accommodate the flow of patients right now,” she said.

As part of phase three, “the actual building is going to be erected, so right now they are pouring the foundations and footers for the building,” she said.

“By the end of this month, you will start to see the structural steel go into place. Basically, it is now building versus the last couple of phases, which were . . . getting the building ready to be constructed.”

The work is being performed by Aldrich+Associates of Bothell.

The current phase started last month and continues to affect much of the area alongside Sheridan Street, part of which is expected to remain closed through November 2016.

During this period, all services remain open, and the hospital expects to care for patients without disruption.

When completed, the new 50,000-square-foot building will change access to the hospital, moving the main entrance to the Sheridan Street side.

It will include an expanded emergency department, an orthopedic clinic and an improved and dedicated cardiology services space supporting the latest in cardiac test procedures.

Also planned is a modern cancer-treatment center and infusion-services area where patients will have access to water views while receiving chemotherapy treatment.

A comprehensive women’s imaging center with state of the art 3-D mammography, ultrasound and bone-density scanning equipment is also part of the plan.

The first phase, which began in May, concentrated on moving and upgrading utility lines, construction of new utility services to support the new building and the reconfiguration parking lots on Ninth Street.

The second phase, which included demolition work, began in mid-September and was completed in October, Burke said.

While traffic along Sheridan Street remains open, sidewalks and bike lanes on the east side of the street between Ninth and Seventh streets are closed to through traffic.

“They still have the Jersey barriers up, and that will remain throughout” construction, Burke said.

“There may be a couple of other traffic revisions as they get closer to the completion work.”

On Seventh Street, “there will be some traffic interruptions probably in the next couple of months because they will be doing some sewer work, and that will impact the traffic flows until 2016,” Burke said.

“That is expected in the near future,” she said, but the contractor “hasn’t given us a definitive date.”

And while the kitchen remains closed for expansion and renovations, “we do have our grab-and-go menu still open,” Burke said.

“The front part of the kitchen where the cashier is and where our grab-and-go options are, that is open and so is the cafe seating area.”

Access to the outpatient clinic continues to be through the administration wing, she said.

The north parking lot located near the emergency department “has been completed and is usable, so people can park by the emergency room department if they need those services,” Burke said.

For more information about the project, visit www.JeffersonHealthcare.org/ESSB.

________

Sequim-Dungeness Valley Editor Chris McDaniel can be reached at 360-681-2390, ext. 5052, or cmcdaniel@peninsuladailynews.com.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading